Transmission and Interconnection. Party A shall be responsible for the design, construction, operation and maintenance of any extension to the Grid ("the Grid Extension") required to interconnect the Power Plant and the Grid. Party B entrusts the EPC Contractor to be responsible for designing and constructing the Interconnection Facilities, in accordance with the terms of the EPC Contract. Party A as the operator of the Power Plant shall be responsible for the operation and maintenance of the Interconnection Facilities. The constraction fund of [***] for the Interconnection Facility and the Grid Extension has been encloded in the total price of EPC Contract as stipulated in section 4.5 of the EPC Contract. [***] Filed separately with the Commission pursuant to a request for confidential treatment. The construction and testing of the Grid Extension by Party A shall proceed simultaneously with the construction and testing of GT#1 Unit of the Power Plant and shall be completed one month before the start-up and synchronization of the GT#1 Unit. Party A's obligation to purchase the Annual Minimum On-Grid Quantity and to pay electricity fee pursuant to this Contract shall be calculated from the Tariff Commencement Date of the GT#1 and GT#2 Units irrespective of whether or not the Grid Extension has been completed by that date.
Appears in 2 contracts
Sources: Operation and Offtake Contract (Aes China Generating Co LTD), Operation and Offtake Contract (Aes China Generating Co LTD)