UC Pool Timeline Clause Samples

UC Pool Timeline i. DY 1: 1. By January 4, 2013, the state must submit to CMS the UC Payment Application template for review and approval. CMS and the state agree to a target approval date of February 28, 2013. CMS reserves the right to not approve the template on the target date if the document is not approvable at that time. 2. Following CMS approval of the UC Payment Application template, hospitals may begin to submit the template for DY 1. 3. By April 30, 2013, the state must submit a revised Attachment J should the state elect to revise the uniform percentages for DY 1. 4. Within 90 days of CMS approval of the UC Payment Application, the state must submit all completed UC Payment Applications in order to qualify for DY 1 UC Payments. 5. By December 31st, hospitals must submit the UC Payment Application for DY 2 in order to qualify to DY 2 UC Payments ii. DY 2 through 4: 1. By December 31st of each year, hospitals must submit to the state the UC Payment Application for the DY beginning January 1. iii. DY 2 through 5: 1. By February 28th of each year, the state must submit a revised Attachment J to CMS for review and approval. 2. By March 31st of each year, the state must submit to CMS the UC Payment Applications and a chart of the estimated UC Payments to each provider for the DY. 3. Within 90 days of the end of the previous DY, the state must submit to CMS: A. The UC Applications submitted by eligible providers; and B. A chart of actual UC Payments for the previous DY.

Related to UC Pool Timeline

  • Project Timeline The Project Timeline establishes a start and end date for each Phase of the Project. Developed during the Initiate & Plan Stage and revised as mutually agreed to, if needed, the timeline accounts for resource availability, business goals, size and complexity of the Project, and task duration requirements.

  • Timeline Contractor must perform the Services and deliver the Deliverables according to the following timeline:

  • Project Specific Milestones In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before July 1, 2021, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.2 Delivery of major electrical equipment. On or before July 15, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

  • Working Day Working Day means a day other than a Saturday, Sunday, or a holiday which is observed by the construction industry in the area of the Place of the Work.

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).