Unauthorized Changes. 6.6.1 No changes to the scope of Work, the Incentive Benchmark or the Substantial Completion Date shall be made, and Contractor shall not be entitled to compensation with respect to such changes to the extent permitted by this Agreement, except in accordance with: (a) a duly issued Change Order executed by both MSG and Contractor; or (b) a Construction Change Directive issued and signed by MSG. 6.6.2 Notwithstanding anything contained in the Contract Documents to the contrary, Contractor shall have no duty to proceed with Changes issued by MSG pursuant to Section 6.1 to the scope of the Work until such time as there is a fully executed Change Order or Construction Change Directive executed by MSG.