Use of Partially Constructed Roads Sample Clauses
The 'Use of Partially Constructed Roads' clause defines the conditions under which a party may access or utilize roads that are not yet fully completed within a project site. Typically, this clause outlines safety requirements, permissible types of vehicles, and any necessary approvals or restrictions before such use is allowed. For example, it may require that only construction vehicles with proper authorization can use these roads, or that certain safety measures must be in place. The core function of this clause is to manage risk and ensure safety by regulating access to incomplete infrastructure, thereby preventing accidents and potential liability during the construction phase.
Use of Partially Constructed Roads. Unless Contracting Officer determines that there is justification under existing conditions and ground conditions permit hauling without undue damage, portions of Specified Roads shall be Substantially Completed prior to their use for hauling timber. When necessary to facilitate construction and protect bridges and roads from damage, timber felled in construction and timber logged directly to the road from areas immediately adjacent thereto may be hauled before road construction is Substantially Completed. Such hauling shall be confined to periods when abnormal soil erosion and damage to National Forest lands will not result.
Use of Partially Constructed Roads. Unless Contracting Officer determines that there is jus- tification under existing conditions, and ground condi- tions permit hauling without undue damage, portions of Specified Roads shall be Substantially Completed prior to their use for hauling timber. When necessary to facil- itate construction and protect bridges and roads from damage, timber felled in construction and timber logged directly to the road from areas immediately adjacent thereto may be hauled before road construction is Sub- stantially Completed. Such hauling shall be confined to periods when abnormal soil erosion and damage to Na- tional Forest lands will not result.
Use of Partially Constructed Roads. Un- less Contracting Officer determines that there is justifica- tion under existing conditions and ground conditions permit hauling without undue damage, portions of Specified Roads shall be Substantially Completed prior to their use for hauling timber. When necessary to facilitate construc- tion and protect bridges and roads from damage, timber felled in construction and timber logged directly to the road from areas immediately adjacent thereto may be hauled before road construction is Substantially Completed. Such hauling shall be confined to periods when abnormal soil erosion and damage to National Forest lands will not re- ▇▇▇▇.
Use of Partially Constructed Roads. Unless Contracting Officer determines that there is justification under existing conditions and ground conditions permit hauling without undue damage, portions of Specified Roads shall be Substantially Completed prior to their use for hauling timber. When necessary to facilitate construction and protect bridges and roads from damage, timber felled in construction and timber logged directly to the road from areas immediately adjacent thereto may be hauled before road construction is Substantially Completed. Such hauling shall be confined to periods when abnormal soil erosion and damage to National Forest lands will not result.
(a) Completion of grading and installation of drainage structures so they will function effectively and
(b) Laying the specified depth of base course, if any. No more than half of Included Timber to be hauled over such portions of road shall be hauled until the base course has been applied. Unless agreed otherwise, specified reconstruction shall be completed on any portion of road prior to hauling on that portion.