Weekly Update. 2.2.1. No later than 14:00 hours each Wednesday prior to the following week (Sunday through Saturday), Seller shall provide an electronic update, in a format specified by Buyer, to the quarterly operations forecast for the next seven (7) calendar days. 2.2.2. The weekly update shall include hourly expected generation and all proposed planned Outages for that week.
Appears in 2 contracts
Sources: Renewable Energy Power Purchase Agreement, Renewable Energy Power Purchase Agreement
Weekly Update. 2.2.12.3.1. No later than 14:00 hours each Wednesday prior to the following week (Sunday through Saturday), Seller shall may provide an electronic update, in a format specified by Buyer, to the quarterly operations forecast Quarterly Operations Forecast for the next seven (7) calendar days.
2.2.22.3.2. The weekly update Weekly Update shall include hourly expected generation and all proposed planned Outages for that weekOutages.
Appears in 1 contract