Common use of When Final Completion Required Clause in Contracts

When Final Completion Required. Minor Items shall be completed as expeditiously as possible, but not later than thirty days after Material Completion of the Work. Permitted Incomplete Work shall be completed as expeditiously as possible, but not later than a date established by the Design Professional. The Design Professional’s Certificate of Final Completion shall not be issued until all Minor Items and Permitted Incomplete Work are completed.

Appears in 42 contracts

Sources: Construction Contract, Construction Contract, Construction Contract

When Final Completion Required. Minor Items Final Completion shall be completed as expeditiously as possible, but obtained not later than thirty (30) days after Material Completion of the Work. Permitted Incomplete Work shall be completed as expeditiously as possible, but not later than a date established by the Design Professional. The Design Professional’s Certificate of Final Completion shall not be issued until all Minor Items and Permitted Incomplete Work are is completed.

Appears in 13 contracts

Sources: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement