Common use of When Final Completion Required Clause in Contracts

When Final Completion Required. Final Completion shall be obtained not later than thirty (30) days after material completion. The Design Professional’s Certificate of Final Completion shall not be issued until all Work is completed.

Appears in 4 contracts

Sources: Construction Contract, Construction Contract, Construction Contract

When Final Completion Required. Final Completion shall be obtained not later than thirty (30) days after material completionthe Material Completion Date. The Design Professional’s Certificate of Final Completion shall not be issued until all Work is completed.

Appears in 1 contract

Sources: Construction Management Agreement

When Final Completion Required. Final Completion shall be obtained not later than thirty (30) days after material completion. The Design Professional’s Professional‟s Certificate of Final Completion shall not be issued until all Work is completed.

Appears in 1 contract

Sources: Design Bid Build Construction Contract