Project Schedule Sample Contracts
Schedule 1 –Project Schedule • April 8th, 2024
Contract Type
FiledApril 8th, 2024
APPENDIX 2FProject Schedule • June 28th, 2021
Contract Type
FiledJune 28th, 2021
• Public Kick-off Meeting March 15, 2004Project Schedule • September 2nd, 2005
Contract Type
FiledSeptember 2nd, 2005
ContractProject Schedule • March 25th, 2014
Contract Type
FiledMarch 25th, 2014
Oak Grove Trestles Project - DRAFT Project Schedule Actions/Deliverables Estimated Date Completion Date Adminstrative Settlement Agreement and Order on Consent for a Site Inspection and an Engineering Evaluation/Cost Analysis (ASAOC) 8/9/2011 Final Work Plan - effective Date of ASAOC 8/9/2011 Sampling And Analysis Plan (SAP) - included in Work Plan 8/9/2011 Health & Safety Plan (HSP) 8/17/2011 Site Investigation (SI) Field Work 9/15/2011 Supplemental Field Work 10/30/2011 Draft SI Summary Report - Including Preliminary Risk Screening and Proposed Relevant Screening Values 11/30/2011 11/30/2011 Forest Service Comments on Draft SI Summary Report 3/30/2012 3/20/2012 PGE submit Final SI Summary Report (30 days after receipt of Forest Service Comments) 5/31/2012 5/31/2012 Forest Service to determine if Engineering Evaluation / Cost Analysis (EE/CA) is required by submitting Action Memorandum to PGE. Spring 2013 If required to perform an EE/CA, the EE/CA will incl
HEALTH TRANSLATION QUEENSLAND PASSPORT AGREEMENT PROJECT SCHEDULEProject Schedule • October 16th, 2023
Contract Type
FiledOctober 16th, 2023
This Project Schedule to the HTQ Research Passport Agreement dated December 2022 incorporates the relevant Terms of the Research Passport Agreement and upon execution, constitutes a separate agreement between the Collaborators [and Third Party Collaborators] named below.
Schedule 1 – WATERSIDE CLOUGHProject Schedule • April 8th, 2024
Contract Type
FiledApril 8th, 2024
ContractProject Schedule • June 16th, 2025
Contract Type
FiledJune 16th, 2025
Project Name: 220 French Landing Renovations SBC# 529/TBD-XX-2025 Design-Bid-Build Schedule Rev 01 06/2023 TASK NAME DURATION START FINISH Project Schedule 1281 days Thu 6/12/2025 Wed 12/13/2028 SBC Project Approval 0 days Thu 6/12/2025 Thu 6/12/2025 ESC Designer Selection 0 days Mon 7/21/2025 Mon 7/21/2025 Execute Designer Agreement 118 days Tue 7/22/2025 Sun 11/16/2025 Design Phase 393 days Mon 11/17/2025 Mon 12/14/2026 Anticipated EDP 0 days Sat Too Early Bidding and Negotiations Phase 110 days Tue 12/15/2026 Sat 4/3/2027 Construction Phase 560 days Sun 4/4/2027 Sat 10/14/2028 Substantial Completion 1 days Sat 10/14/2028 Sat 10/14/2028 Punchlist and Final Completion 30 days Sun 10/15/2028 Mon 11/13/2028 Project Delivery 30 days Tue 11/14/2028 Wed 12/13/2028
Dana Point Harbor Commerical Core, Hotel, and MarinaProject Schedule • April 5th, 2024
Contract Type
FiledApril 5th, 2024
EXHIBIT B: PROJECT SCHEDULEProject Schedule • May 12th, 2014
Contract Type
FiledMay 12th, 2014
[To be agreed upon by the parties and to include, at a minimum, the Completion Deadlines (for NTP 1 through NTP 5), and Final System Acceptance]