Date for Substantial Completion definition

Date for Substantial Completion means the date for the Substantial Completion of the Works, being the date identified as such in the Full Connection Offer or such later date as may be established pursuant to Clause 5.1;
Date for Substantial Completion meanss the date indicated in the contract by which the Supplier is required to achieve Substantial Completion, as amended in accordance with the contract. If no Date for Substantial Completion is indicated in the contract, the date shall be a reasonable date by which the Supplier is to achieve Substantial Completion by.
Date for Substantial Completion a date specified in the Quotation or advised by us to you in

Examples of Date for Substantial Completion in a sentence

  • No increase in the Contract Sum shall be made and no extension of the Scheduled Date for Substantial Completion shall be allowable, however, for any conditions (whether or not indicated by the Contract Documents) ascertainable by a careful Project Site inspection by Contractor.

  • The Contractor may direct the Sub-Contractor to re- sequence the work under the Sub-Contract so as to ensure that Completion is achieved by the Date for Substantial Completion or to accommodate the work under the Head Contract.

  • If the Contractor does not have its Work on the Project Substantially Complete by the specified Date for Substantial Completion or Finally Complete by the Date of Final Completion, the Contractor shall pay the Owner (and the Owner may set off from sums coming due the Contractor) Liquidated Damages in the per diem amounts as set forth in the following tables, whichever may be applicable.

  • Any rejection of a bid or required re-bid under this Section 11.6 shall not be the basis for recovery as a Cost of the Work or an adjustment to the Incentive Benchmark or the Date for Substantial Completion or the Long Stop Completion Date.

  • If the Contractor does not have its Work on the Project Substantially Complete by the specified Date for Substantial Completion or Finally Complete within forty- five (45) days of achieving Substantial Completion, the Contractor shall pay the Owner (and the Owner may set off from sums coming due the Contractor) Liquidated Damages in the per diem amounts as set forth in the following tables, whichever may be applicable.

  • If a condition is encountered by Contractor which satisfies subsections (1) and (2) above, Contractor shall be entitled to an extension of the Scheduled Date for Substantial Completion, as reasonably determined by Owner, and an adjustment to the Contract Sum in accordance with the provisions of Article 5.

  • Owner and Contractor recognize that time is of the essence of this Agreement and that Owner will suffer financial loss in the form of lost revenues and contract administration expenses (including project management and consultant’s expenses), delay and loss of public use if Work is not completed by the Scheduled Date for Substantial Completion plus any extensions thereof allowed in accordance with the Contract Documents.

  • A “Change Order” is a written instrument prepared by the Construction Manager or Owner’s Representative at the request of Contractor for Owner’s approval and, if approved by Owner, signed by Owner and Contractor, setting forth their agreement upon (i) a change in the Work, if any; (ii) the amount of adjustment in the Contract Sum, if any; and (iii) the amount of any adjustment in the Scheduled Date for Substantial Completion, if any.

  • Contractor shall not make any change in the Work or be entitled to any adjustment in the Contract Sum or the Scheduled Date for Substantial Completion, except as provided in a Change Order signed by Owner or Owner’s Representative or in accordance with the procedure set forth in Section 5.3 regarding Field Order Requests.

  • A Change Order will be issued to cover any adjustments in the Contract Sum or the Scheduled Date for Substantial Completion necessarily caused by such suspension.


More Definitions of Date for Substantial Completion

Date for Substantial Completion means the date for the Substantial Completion of the Design and Build Works, being the date identified as such in the Conceptual Design Study Report or such later date as may be established pursuant to Clause 6;
Date for Substantial Completion means the date stated in Item 8 of the Schedule as amended in accordance with the Subcontract;

Related to Date for Substantial Completion

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Substantial Completion Date means the required date for Substantial Completion of the Project. The Substantial Completion Date can be adjusted only by written Change Order.

  • Certificate of Substantial Completion means the certificate executed by the Design Professional, Owner, and Contractor that documents to the best of the Design Professional’s and Owner’s knowledge and understanding, Contractor’s sufficient completion of the Work in accordance with the Contract, so as to be operational and fit for the use intended.

  • Mechanical Completion means that (a) all components and systems of the Project have been properly constructed, installed and functionally tested according to EPC Contract requirements in a safe and prudent manner that does not void any equipment or system warranties or violate any permits, approvals or Laws; (b) the Project is ready for testing and commissioning, as applicable; (c) Seller has provided written acceptance to the EPC Contractor of mechanical completion as that term is specifically defined in the EPC Contract.

  • Final Completion means acceptance of the Work by the County as evidenced by its signature upon Final Certificate of Completion and approval thereof by the Board of County Commissioners. The Final Certificate of Completion shall be signed only after the County has assured itself by tests, inspection or otherwise that all of the provisions of the Contract have been carried out to its satisfaction.