Guaranteed Final Completion Date definition

Guaranteed Final Completion Date has the meaning set forth in Section 6.8.
Guaranteed Final Completion Date has the meaning set forth in Section 18.1, as may be extended only in accordance with the express terms of this Agreement.
Guaranteed Final Completion Date means the Guaranteed Final Completion Date identified in the Schedule, as the same may be amended from time-to-time in accordance with this Contract.

Examples of Guaranteed Final Completion Date in a sentence

  • The Guaranteed Final Completion Date as of the date of this Change Order therefore is March 31, 2008.

  • The Guaranteed Final Completion Date shall only be adjusted by Change Order as provided under this Agreement.

  • Subject to Article 17, Contractor shall perform the Work in accordance with the Construction Schedule, as may be amended from time to time in accordance with the terms of this Agreement, so as to achieve Block Substantial Completion for each Block by the Guaranteed Block Substantial Completion Dates, Facility Substantial Completion by the Guaranteed Facility Substantial Completion Date and Final Completion by the Guaranteed Final Completion Date.

  • Unless set forth in a Change Order executed by the Parties, the implementation of any Delay Response Plan shall not change the Guaranteed Block Substantial Completion Dates, the Guaranteed Facility Substantial Completion Date or the Guaranteed Final Completion Date.

  • The Guaranteed Final Completion Date as of the date of this Change Order therefore is , 20 .


More Definitions of Guaranteed Final Completion Date

Guaranteed Final Completion Date means the earlier of (i) one hundred and eighty (180) calendar days after the Facility Substantial Completion Date and (ii) October 16, 2009. [ASA, CA, EPC, O&M, Schedule Z]
Guaranteed Final Completion Date means:
Guaranteed Final Completion Date means the date that is 365 Days after the Substantial Completion Date, which date may be adjusted pursuant to the terms and conditions of the Prime Contract.
Guaranteed Final Completion Date means, with respect to any Plant, the “Guaranteed Final Completion Date,” as defined in the Design Build Contract for such Plant.
Guaranteed Final Completion Date means July 9, 2010. [ASA, CA, EPC, O&M, Schedule Z]
Guaranteed Final Completion Date has the meaning set forth in the EPC Contract as in effect on the date thereof.
Guaranteed Final Completion Date means March 15, 2022.