Material Delay definition

Material Delay means with respect to all Exclusive Air Transportation Services operated by any of the Air Carriers, an arrival greater than 15 minutes after the scheduled arrival time for any Blade Flight; provided, however, that in determining whether a flight has experienced a “Material Flight Delay,” delays attributable to factors outside the relevant Air Carriers’ direct control shall be excluded from this definition.
Material Delay means a delay in the expiration or termination of the HSR waiting period or in obtaining any Material Approval until after the later of (x) the 120th day following the date of the execution and delivery of this Agreement in the case of HSR (or 120 days following the date of this Agreement, subject to extension on a day-by-day basis if and to the extent the Company fails to promptly respond to reasonable requests by DuPont with respect to filings and information required in connection with the Merger pursuant to Section 5.8) and (y) the satisfaction or waiver of all conditions set forth in Article VI hereof other than those set forth in Section 6.2(a) and (b) and those that are not satisfied by reason of the failure of the HSR waiting period to have expired or of any Material Approval to have been obtained.
Material Delay. (i) a late delivery of the Product caused by GRC's instructions, changes, or modifications to the Products (including purchase orders for quantities of Product in excess of that contemplated by the forecasts described in Section 2.6) or (ii) any period of no more than two (2) weeks during which Product is not available for delivery to GRC FOB Ningbo Harbor, China due to a delay caused by a decision of a United States or Chinese governmental agency to review any Product which is the subject of any shipment.

Examples of Material Delay in a sentence

  • In addition, the Material Delay Fee shall be charged against Contractor for failure to comply with the Emergency Call Out requirements described in the Scope of Services.

  • If Landlord and Tenant disagree about the duration of any Hazardous Material Delay, they shall utilize the above-referenced dispute resolution procedures.

  • The "Rent Commencement Date" shall be the date that is one hundred sixty-eight (168) days after the Commencement Date; provided, however, that the Rent Commencement Date shall be postponed by one (1) day for each day of: (a) Landlord Delay, (b) delay attributed to a Tenant Force Majeure, and (c) Hazardous Material Delay.

  • City’s right to charge and receive payment of the Material Delay Fee is in addition to any and all other rights and remedies available to City under this Agreement or at law and in equity resulting from a material delay in performance by Contractor.

  • A "Hazardous Material Delay" is any delay to the Tenant Improvement Work in deviation from the written schedule provided to Landlord which is the direct result of Environmental Work that is or is required to be performed by Landlord or its environmental consultant, including, without limitation, any delay directly resulting from any additional approvals that Tenant or Landlord may have to obtain from governmental entities as a result of such Environmental Work.

  • City may withhold from Contractor an amount payable to Contractor under this Agreement that is equal to the amount of the Material Delay Fee(s) charged against Contractor pursuant to this Section.

  • In the event of a Hazardous Material Delay, the Rent Commencement Date shall be extended as set forth in Section 3.2. In addition, Landlord shall pay Tenant an amount equal to One Thousand Six Hundred Sixty-Seven Dollars ($1,667) for every day of Hazardous Material Delay.

  • If a Force Majeure Event should cause a Material Delay, the Final Completion Date shall be extended for such additional period of time as may be reasonably necessary to cure such Force Majeure Event and to permit expeditious completion of the construction, renovation, installation, equipping, and improvement of the Project, but in any event for a period ending not later than [ ], without the prior written consent of the City.

  • In the event there will be a Hazardous Material Delay of nine (9) months or more, and Tenant provides Landlord with written notice that it desires to terminate this Lease, this Lease shall terminate effective as of the date of such notice if Landlord and Tenant agree, or it is otherwise determined through the above-referenced dispute resolution procedures, that there will be a Hazardous Material Delay of nine (9) months or more.

  • The Construction Agent shall give the City prompt written notice of the occurrence of any Force Majeure Event, as defined below, with respect to the Project that has caused, or is reasonably likely to cause a Material Delay.


More Definitions of Material Delay

Material Delay means any event or condition (or related series of events or conditions) that causes or results in a delay (or total stoppage) in the progress of the construction, renovation, installation, equipping, and improvement of the Project of such duration that the construction, renovation, installation, equipping, and improvement of the Project cannot reasonably be completed within the Cost Budget on or before the Final Completion date.
Material Delay means with respect to the consummation of any of the transactions contemplated hereby, a delay for more than 30 days or a delay beyond June 12, 1998, whichever is earlier.
Material Delay means a delay that is more than thirty (30) days from the Project Completion Date. “Notice Address” means:
Material Delay means any event or condition (or related series of events or conditions) that causes or results in a delay (or total stoppage) in the progress of the Project Improvements of more than 30 days.
Material Delay means any unanticipated delay of greater than [***] consecutive days in the timeline for a Party to conduct its respective activities under the Rescue Plan or Study Plan for Part B2, including but not limited to (i) non-scientific events, including for example, a Force Majeure Event, or (ii) scientific events independent of the performance of Product Candidate features, but which materially impacts the ability to assess the data package for Part B2, including for example, failure of the positive/negative control to work as expected or failure of the experimental model.
Material Delay means any event or condition (or related series of events or conditions) that causes or otherwise results in a delay (or total stoppage) in the progress of the Global Development Plan of more than [***] except (a) for any event or condition outside the reasonable control of Fulcrum that is not directly related to a breach by Fulcrum of this Agreement; (b) if such event or condition is substantially a result of any inaction or action by Sanofi, its Affiliates or Sublicensees; (c) if such event or condition is a result of Fulcrum’s reasonable response to guidance from or action or inaction by a Regulatory Authority or Governmental Authority (such as a clinical hold, recall or withdrawal); (d) for a Force Majeure Event; or (e) for any delay or stoppage mutually agreed upon by the Parties.

Related to Material Delay

  • Developmental delay means that a child has not reached developmental milestones expected for his or her chronological age as measured by qualified professionals using appropriate diagnostic instruments and/or procedures.

  • Material Deviation refers to any contents or characteristics of the proposal that is significantly different from an essential aspect or requirement of the RFP, and : (i) substantially alters the scope and quality of the requirements; (ii) limits the rights of UNDP and/or the obligations of the offeror; and (iii) adversely impacts the fairness and principles of the procurement process, such as those that compromise the competitive position of other offerors.

  • Material Default means a material breach of this Framework Agreement and/or, breach by the Supplier of any of the following Clauses: Clause 8 (Warranties and Representations), Clause 9 (Prevention of Bribery and Corruption), Clause 13 (Statutory Requirements and Standards), Clause 14 (Non-Discrimination), Clause 15 (Provision of Management Information), Clause 16 (Management Charge), Clause 17 (Records and Audit Access), Clause 22 (Data Protection), Clause 23 (Freedom of Information) and Clause 31 (Transfer & Sub-contracting);

  • Material date means the date of publication of notification of various controlled area declared as under:-

  • Contractual Delivery Date means the stipulated date on which the contractor shall attain