Request for a Change Order definition
Examples of Request for a Change Order in a sentence
Each written Request for a Change Order must be accompanied by written suggestions where costs can be reduced to offset the Change Order increase requested or a written certification stating that the Contractor has reviewed the work to be performed and cannot identify areas where costs can be reduced.
If Design-Builder does not comply in full with the requirements of Sections 12.3 and 12.4, VPRA may provide written notice rejecting Design-Builder’s Request for a Change Order within the forty five (45)-Day time period and such notice shall identify the deficiencies within Design-Builder’s submittal.
Pending resolution of the Contractor’s Request for a Change Order, the Contractor shall maintain its progress with the Work.
Pending resolution of the Contractor’s Request for a Change Order, the Contractor shall continue to perform all Work including, at the written request of City that work associated with the pending Request for Change Order.
A Request for a Change Order must be submitted in writing to the Engineer no later than thirty-five (35) days after the Contractor submitted its supplemental information pursuant to Paragraph 5.1(A)(2).
If the cause of the delay is not such that would give rise to an excusable delay pursuant to paragraph 6 of the Agreement, the Owner, in the exercise of its sole discretion, may grant or deny the Request for a Change Order.
All documentation supporting the Request for a Change Order, including but not limited to all cost records, schedule analysis, and the documents identified in §00700, ¶ 3.11, Maintenance and Inspection of Documents, that are in any way relevant to the Contractor’s Request for Change Order.
Pending resolution of the Contractor’s Request for a Change Order, the Contractor shall continue to perform all Work including, at the written request of the County that work associated with the pending Request for Change Order.
No later than seven days after the event, directive, instruction, comment or other reason that the Contractor believes is a basis for a change order, the Contractor shall provide the County with the Contractor’s Request for a Change Order.