The "Addenda and Interpretations" clause establishes the process for issuing official updates, clarifications, or modifications to the contract documents after they have been initially released. Typically, this clause allows the contracting parties or the issuing authority to provide written addenda or formal interpretations in response to questions, ambiguities, or changes that arise during the bidding or contract performance period. For example, if bidders need clarification on a specification, the owner may issue an addendum to all bidders to ensure everyone has the same information. The core function of this clause is to maintain consistency and clarity in contract documents, preventing misunderstandings and ensuring all parties are operating with the most current and accurate information.
ADDENDA AND INTERPRETATIONS. A. No interpretation of the meaning of the Drawings, Specifications or other pre-bid documents or Contract Documents shall be made to any Bidder orally. B. Any and all such interpretations and any supplemental instructions will be in the form of written Addenda to the Contract Documents which, if issued, will be mailed, shipped or faxed to all prospective Bidders (at the respective addresses furnished) at least seventy-two (72) hours (exclusive of weekends and holidays) prior to the date fixed for the opening of Bids. C. Failure of Bidders to receive or acknowledge any Addendum shall not relieve them of any obligation under the Bid or the Contract Documents. All Addenda shall become part of the Contract Documents and obligations there under binding.
ADDENDA AND INTERPRETATIONS. No interpretation of the meaning of the bidding documents will be made to any bidder orally. Every request for such interpretation should be in writing addressed to the Parks and Recreation Director of the City of Fremont, Nebraska, at the address given in the Notice to Bidders, and to be given consideration must be received at least seven (7) days prior to the date fixed for the opening of bids.
ADDENDA AND INTERPRETATIONS. No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally. All information given to bidders other than by means of the plans, specifications, or by addenda, as described below, is given informally and shall not be used as the basis of a claim against the Owner. Every request for such interpretation should be in writing addressed to the Amesbury Housing Authority Purchasing Department at ▇▇▇ ▇▇▇▇ ▇▇ ▇▇▇▇▇▇▇▇ ▇▇ ▇▇▇▇▇ and to be given consideration must be received at least seven (7) days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the Contract Documents. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under this bid as submitted. All addenda so issued shall become part of the Contract Documents.
ADDENDA AND INTERPRETATIONS. No interpretation of the meaning of the specifications, or other contract documents will be made to any bidder orally. Every request for such interpretation should be in writing, addressed to the Purchasing Agent, Augusta School Department, ▇▇ ▇▇▇▇▇▇ ▇▇▇▇▇, Suite 3, Augusta, ME 04330, and to be given consideration, must be received at least five (5) days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be mailed or faxed to all prospective bidders, at the respective addresses furnished for such purposes, not later than one (1) day prior to the date fixed for the opening of bids. Failure of any bidder to receive any such addendum or interpretation shall not relieve any bidder from any obligation under their bid as submitted. All addenda so issued shall become part of the contract documents.
ADDENDA AND INTERPRETATIONS. No interpretations of the meaning of the Contract Documents will be made to any Bidder orally. Any and all revisions, interpretations or clarifications will be in the form of written Addenda to the Contract Documents which, if issued, will be provided no later than seven (7) days (Saturday, Sunday or holidays excepted) prior to the date for acceptance of bids to any person who has submitted a Bid or who has received a bid package in writing by fax and/or email. All Addenda so issued shall become part of the Contract Documents. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. Each Bidder shall ascertain, prior to submitting its Bid that it has received all Addenda, if any, issued and shall acknowledge receipt of all such Addenda on the Acknowledgment of Receipt of Addenda Form provided by the BOROUGH or like form.
ADDENDA AND INTERPRETATIONS. No interpretations of the meaning of the plans, specifications or other contract documents will be made orally to any bidder. Prospective bidders must request such interpretation in writing as instructed in the bid package. To be considered, such request must be received by the Questions and Answers deadline as indicated in ▇▇▇▇▇▇▇.▇▇▇. Material changes, if any, to the scope of services or bidding procedures will only be transmitted by written addendum. It is the bidder’s responsibility to verify if addendums have been issued in ▇▇▇▇▇▇▇.▇▇▇. Failure of any bidder to receive any such addenda or interpretation shall not relieve any bidder from any obligation under his bid as submitted. All addenda so issued shall become a part of the contract document. Bidder shall verify in ▇▇▇▇▇▇▇.▇▇▇ that he has all addenda before submitting a bid. FORMS OF PROPOSALS - Each proposal and its accompanying statements must be made on the blanks provided. THE FORMS MUST BE SUBMITTED ELECTRONICALLY, IN GOOD ORDER INSTRUCTIONS TO BIDDERS (continued) The above bond or check shall be a guarantee that the bidder will, if necessary, promptly execute a satisfactory contract and furnish good and sufficient bonds. As soon as a satisfactory contract has been executed and the bonds furnished and accepted, the check or bond accompanying the proposal of the successful bidder will be returned to him. The certified or other checks or bid bonds of the unsuccessful bidders will be returned to them upon the acceptance of the bid of the successful bidder. If the successful bidder shall not enter into, execute, and deliver such a contract and furnish the required bonds within ten (10) days after receiving notice to do so, the certified or other check or bid bond shall immediately become the property of the City of Fort Lauderdale as liquidated damages. Retention of such amount shall not be construed as a penalty or forfeiture.
ADDENDA AND INTERPRETATIONS. A. No interpretation of the meaning of the Drawings, Specifications or other pre-bid documents or Contract Documents shall be made to any Bidder orally. B. Any and all such interpretations and any supplemental instructions will be in the form of written Addenda to the Contract Documents which, if issued, will be mailed, shipped or faxed to all prospective Bidders (at the respective addresses furnished) prior to the date fixed for the opening of Bids. C. Failure of Bidders to receive or acknowledge any Addendum shall not relieve them of any obligation under the Bid. All Addenda shall become part of the Contract Documents.
ADDENDA AND INTERPRETATIONS. No different interpretation of the meaning of the bidding documents will be made to any bidder orally. Every request for such interpretation should be made to ▇▇▇▇ ▇▇▇▇▇▇▇ (▇▇▇) ▇▇▇-▇▇▇▇ or ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇ (▇▇▇) ▇▇▇-▇▇▇▇, or mailed to the Department of Utilities at the address given in the Notice to Bidders, and to be given consideration must be received at least seven (7) days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda which, if issued, will generally be mailed by certified mail with return receipt requested to all parties recorded as having received bidding documents (at the respective addresses furnished for such purposed), prior to the date fixed for the opening of bids. All addenda so issued shall become part of the contract documents. Bidders will be responsible for verifying that they have received all addenda issued by listing the addendum number on the Bid Proposal where it is indicated "Acknowledgment of Receipt of Addendums".
ADDENDA AND INTERPRETATIONS. No oral interpretation of the meaning of the plans, specifications or other pre-bid documents will be made. Requests for clarification should be made in writing to the A/E or Project Manager identified in the Invitation for Construction Bids and to be given consideration must be received at least five (5) days prior to the date fixed for the opening of bids. Any interpretations, corrections or changes will be issued in the form of written addenda and will be transmitted to all who are known to have received a complete set of biding documents by telephone, fax or other appropriate means with immediate follow-up with written addenda. Should the original Bid Date be postponed, the new Bid Date shall be no earlier than the fifth (5th) calendar day after the date of issuance of the addendum postponing the original Bid Date. Failure of any Bidder to receive any such addendum or interpretation shall not relieve such Bidder from any obligation under its bid as submitted. All addenda so issued shall become part of the Contract documents.
ADDENDA AND INTERPRETATIONS. No interpretation of the meaning of plans, specifications or other pre-bid documents will be made to any bidder orally. Every request for such interpretation should be in writing addressed to the ▇▇▇▇ ▇. ▇▇▇▇, Director of Procurement; Procurement Department; Suite ▇▇▇; ▇▇▇ ▇▇▇▇▇▇▇ ▇▇▇▇▇▇; ▇▇▇▇▇▇▇, ▇▇ ▇▇▇▇▇ and to be given consideration must be received at least ten days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, if issued, will be sent by facsimile or U.S. Mail to all prospective bidders (at the respective addresses furnished for such purposes), not later than five days prior to the date fixed for the opening of bids. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the Contract Documents.