Adjustment of Scheduled Substantial Completion Date Clause Samples

Adjustment of Scheduled Substantial Completion Date. If Contractor’s Baseline Schedule submitted pursuant to Section 13.1.2 shows a projected date for Substantial Completion more than thirty (30) days earlier than the Scheduled Substantial Completion Date, Contractor agrees that Owner may, at no cost to Owner, decrease the Scheduled Substantial Completion Date by issuance of an appropriate Change Order changing the Scheduled Substantial Completion Date to the date reflected in the Baseline Schedule. The specific intent of this Section 13.1.4 is to ensure that Contractor does not have a right to seek recovery from Owner on the grounds that it was entitled to achieve Substantial Completion of the Project earlier than the Scheduled Substantial Completion Date.

Related to Adjustment of Scheduled Substantial Completion Date

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.