Common use of After Final Completion Clause in Contracts

After Final Completion. If, within one year after the date of Substantial Completion of the Work or a designated portion thereof, or any longer period prescribed by any special guarantee required by the Contract Documents, any of the Work is found to be not in accord with the requirements of the Contract Documents, Contractor shall cause the Work to be corrected promptly after receipt of written notice from Owner to do so unless Owner has previously given Contractor a written acceptance of such condition. This obligation under this paragraph shall survive acceptance of and payment for the Work under this Agreement. The obligation under this paragraph shall also survive termination of this Agreement for cause. Owner shall give such notice promptly after discovery of the condition.

Appears in 2 contracts

Sources: Engineering, Procurement & Construction Management Agreement, Engineering, Procurement & Construction Management Agreement (Hoku Scientific Inc)

After Final Completion. If, within one (1) year after the date of Substantial Completion of the Work or a designated portion thereof, or any longer period prescribed by any special guarantee required by the Contract Documents, any of the Work is found to be not in accord with the requirements of the Contract Documents, Contractor Contractor, at no expense to Owner, shall cause the Work to be corrected promptly after receipt of written notice from Owner to do so unless Owner has previously given Contractor a written acceptance of such condition. This obligation under this paragraph shall survive acceptance of and payment for the Work under this Agreement. The obligation under this paragraph shall also survive termination of this Agreement for cause. Owner shall give such notice promptly after discovery of the condition.

Appears in 1 contract

Sources: Engineering, Procurement, and Construction Agreement (Embrex Inc/Nc/)