Availability and maintenance. (a) In the period beginning with the Commencement Date and ending on the Availability Date the Contractor must ensure that the RWS Infrastructure: (i) consists of the Traffic Lanes as defined in Table 1 of Schedule 2, Schedule 1 (Traffic Lane Definitions, Category-A Requirements and Category-B Requirements in the Development Phase); (ii) at least consists of the objects listed in respect of this period in Schedule 9, Part 1, paragraph 2.1 (RWS Infrastructure Objects); and (iii) is maintained in accordance with the Category A Requirements applicable to this period and the Category B Requirements. [If the Contractor wishes that a part of the RWS Infrastructure created after the Commencement Date is made available for public traffic prior to the Availability Date, the Contractor must demonstrate that, on the date of submitting the request for opening to the corresponding authorities, the relevant portion of the RWS Infrastructure meets the relevant Opening Requirements as well as the Category A and Category B requirements in effect during the period beginning on the Availability Date and ending on the Completion Date.] (b) In the period beginning on the day after the Availability Date and ending on the Completion Date the Contractor must ensure that the RWS Infrastructure: (i) consists of the Traffic Lanes as defined in Table 1 of Schedule 2, Schedule 2 (Traffic Lane Definitions, Category-A Requirements and Category-B Requirements in the Operational Phase); (ii) at least consists of the objects listed in respect of this period in Schedule 9, Part 1, paragraph 2.1 (RWS Infrastructure Objects); and (iii) is maintained in accordance with the Category A Requirements applicable to this period and the Category B Requirements. (c) In the period beginning on the day after the Completion Date and ending on the Expiry Date the Contractor must ensure that the RWS Infrastructure: (i) consists of the Traffic Lanes as defined in Table 1 of Schedule 2, Schedule 2 (Traffic Lane Definitions, Category-A Requirements and Category-B Requirements in the Operational Phase); (ii) at least consists of the objects listed in respect of this period in Schedule 9, Part 1, paragraph 2.1 (RWS Infrastructure Objects); and (iii) is maintained in accordance with the Category A Requirements applicable to this period and the Category B Requirements.
Appears in 2 contracts
Sources: DBFM Agreement, DBFM Agreement
Availability and maintenance. (a) In Throughout the period beginning with on the Commencement Date and ending on the Availability Date Date, the Contractor must ensure that the RWS Infrastructure:
(i) consists comprises of the Traffic Lanes as defined referred to in Table 1 of Schedule 2, Schedule Table 1, Annex 1 (Traffic Lane Definitions, Category-A Requirements definitions and Category-B Requirements availability requirements in the Development PhasePeriod);
(ii) at least consists comprises of the objects listed in respect of this period the Commencement Date in Schedule 9, Part 1, paragraph 2.1 Table 1 (RWS Infrastructure Objects); and
(iii) is maintained in accordance with the Category A Requirements applicable to this period and the Category B Requirements. [If the Contractor wishes that a part of the RWS Infrastructure created after the Commencement Date is made available for public traffic prior to the Availability Date, the Contractor must demonstrate that, on the date of submitting the request for opening to the corresponding authorities, the relevant portion of the RWS Infrastructure meets the relevant Opening Requirements as well as the Category A and Category B requirements in effect during Transition requirements.
(b) Throughout the period beginning on the Availability Date and ending on the Completion Date.]
(b) In the period beginning on the day after the Availability Date and ending on the Completion Date , the Contractor must ensure that the RWS Infrastructure:
(i) consists comprises of the Traffic Lanes as defined referred to in Table 1 of Schedule 2, Schedule Table 1, Annex 2 (Traffic Lane Definitions, Category-A Requirements definitions and Category-B Requirements availability requirements in the Operational PhaseAvailability Period);
(ii) at least consists comprises of the objects listed in respect of this period the Availability Date in Schedule 9, Part 1, paragraph 2.1 Table 1 (RWS Infrastructure Objects); and
(iii) is maintained in accordance with the Category A Requirements applicable to this period and the Category B RequirementsTender requirements.
(c) In Throughout the period beginning on the day after the Completion Date and ending on the Expiry Date Date, the Contractor must ensure that the RWS Infrastructure:
(i) consists comprises of the Traffic Lanes as defined referred to in Table 1 of Schedule 2, Schedule Table 1, Annex 2 (Traffic Lane Definitions, Category-A Requirements definitions and Category-B Requirements availability requirements in the Operational PhaseAvailability Period);
(ii) at least consists comprises of the objects listed in respect of this period the Completion Date in Schedule 9, Part 1, paragraph 2.1 Table 1 (RWS Infrastructure Objects); and
(iii) is maintained in accordance with the Category A Requirements applicable to this period and the Category B RequirementsCompletion requirements.