Before Substantial Completion. 12.4.1.1 The Design-Builder shall promptly correct Work rejected by the Engineer or failing to conform to the requirements of the Contract Documents, whether discovered before or after Substantial Completion and whether or not fabricated, installed or completed. Costs of correcting such rejected Work, including additional testing and inspections and compensation for the Engineer’s services and expenses made necessary thereby shall be at the Design-Builder’s expense.
Appears in 3 contracts
Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement