Common use of Change of Scope Clause in Contracts

Change of Scope. 13.1.1 The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 47 contracts

Sources: Engineering, Procurement and Construction Agreement, Draft Contract Agreement, Draft Contract Agreement (Dca)

Change of Scope. 13.1.1 The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/modifications or alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 24 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement

Change of Scope. 13.1.1 14.1.1 The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor Concessionaire to make modifications/modifications or alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor Concessionaire to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 1314.

Appears in 3 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Change of Scope. 13.1.1 The Authority Employer may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/alterations to the Works ("Change of Scope") before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 3 contracts

Sources: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement

Change of Scope. 13.1.1 The Authority Employer may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 3 contracts

Sources: Epc Agreement, Epc Agreement, Contract Agreement for Design and Construction

Change of Scope. 13.1.1 The Authority may, notwithstanding anything to the contrary contained in this Contract Agreement, require the Contractor to make modifications/modifications or alterations to the Works (“Change of Scope”) before the issue of the Completion Project Commissioning Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 2 contracts

Sources: Draft Contract Agreement, Contract Agreement

Change of Scope. 13.1.1 The Authority Employer may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 1 contract

Sources: Demonstration Agreement

Change of Scope. 13.1.1 13.1.1. The Authority may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 1 contract

Sources: Epc Agreement

Change of Scope. 13.1.1 The Authority Authority/GMDA may, notwithstanding anything to the contrary contained in this Agreement, require the Contractor to make modifications/alterations to the Works (“Change of Scope”) before the issue of the Completion Certificate either by giving an instruction or by requesting the Contractor to submit a proposal for Change of Scope involving additional cost or reduction in cost. Any such Change of Scope shall be made and valued in accordance with the provisions of this Article 13.

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement