Compaction and Rutting Clause Samples

The Compaction and Rutting clause sets standards for the density and surface integrity of materials, such as soil or asphalt, used in construction projects. It typically requires that these materials be compacted to a specified level to prevent future settlement or deformation, and that any rutting—depressions or grooves caused by traffic or equipment—be minimized or repaired. By establishing these requirements, the clause ensures the long-term durability and safety of constructed surfaces, addressing issues that could lead to costly repairs or unsafe conditions if left unchecked.
Compaction and Rutting. A. Unless the Landowner opts to do the restoration work, after the topsoil has been replaced, all areas that were traversed by vehicles and Construction and/or Deconstruction equipment will be ripped at least 18 inches deep, and all pasture and woodland will be ripped at least 12 inches deep to the extent practicable. The existence of tile lines or underground utilities may necessitate less depth. The disturbed area will then be disked. Decompaction shall be conducted according to the guidelines provided in Appendices A and B. B. To the extent practicable, all ripping and disking will be done at a time when the soil is dry enough for normal tillage operations to occur on land adjacent to the right-of-way. C. The Facility Owner will restore all rutted land to a condition as close as possible to its original condition. D. If there is any dispute between the Landowner and the Facility Owner as to what areas need to be ripped/disked or the depth at which compacted areas should be ripped/disked, the appropriate County SWCD’s opinion shall be considered by the Facility Owner and the Landowner.
Compaction and Rutting. The Company will rip or pay to rip all areas that were traversed by vehicles and/or construction equipment according to the following, unless otherwise stated in an Underlying Agreement between the Company and the Landowner: cropland shall be ripped to a depth of 18 inches, pasture land shall be ripped at least 16-inches deep, and woodland shall be ripped at least 12-inches deep if stumps were removed from the ROW during clearing/grading activities. The existence of tile lines, underground utilities, or shallow topsoil and subsoil horizons may necessitate less depth. The existence of tile lines, underground utilities, or shallow topsoil and subsoil horizons may necessitate less depth. Decompaction shall be conducted according to the guidelines provided in Appendices A and B. When done correctly, with the proper equipment and soil conditions, ripping across any Agricultural Land should only take one pass. Additional passes should only be conducted with the Landowner’s approval and if the previous pass did not sufficiently shatter the soil and is not precluded by the Landowner’s Underlying Agreement. Decompaction of compacted ROW topsoil shall occur after importing of topsoil (if needed) and land leveling to return the ROW to pre-construction contours. The entire ripped area may then be disced in preparation for seeding, as necessary; however, additional tracking/driving on the ROW after decompaction activities risks re-compacting or rutting the area. The Company shall use its Best Efforts to restore all compacted or rutted land as a result of the Electric Line Project to its pre-construction condition, in compliance with local, state, and federal regulations. All ripping and discing shall be done at a time when the soil is dry enough for normal tillage operations to occur on undisturbed farmland adjacent to the areas to be ripped or disced. If there is a dispute between the Landowner and the Company with regard to compaction, rutting, which areas need to be ripped, or the depth at which ripping should occur, the Landowner and the Company shall consult the local SWCD.
Compaction and Rutting. A. Unless the Landowner opts to do the restoration work on compaction and rutting, after the topsoil has been replaced, all areas that are not directly under photovoltaic panels that were traversed by vehicles and Construction and/or Deconstruction equipment will be ripped at least 18 inches deep, and all pasture and woodland will be ripped at least 12 inches deep to the extent practicable. The existence of tile lines or underground utilities may necessitate less depth. The disturbed area will then be disked. Decompaction shall be conducted according to the guidelines provided in Appendices A and B. B. All ripping and disking will be done at a time when the soil is dry enough for normal tillage operations to occur on land adjacent to the right-of-way. C. The Commercial Solar Energy Facility Owner will restore all rutted land to a condition as close as possible to its original condition. D. If there is any dispute between the Landowner and the Commercial Solar Energy Facility Owner as to what areas need to be ripped/disked or the depth at which compacted areas should be ripped/disked, the appropriate County Soil and Water Conservation District’s opinion shall be considered by the Owner and the Landowner.

Related to Compaction and Rutting

  • Compaction 11.1 Concrete shall be thoroughly compacted and fully worked around the reinforcement, around embedded fixtures and into corners of the formwork. 11.2 Concrete shall be compacted using mechanical vibrators complying with IS 2505, IS 2506, IS 2514 and IS:4656. Over vibration and under vibration of concrete are harm full and shall be avoided. Vibration of very wet mixes shall also be avoided. Whenever vibration has to be applied externally, the design of formwork and the disposition of vibrators shall receive special consideration to ensure efficient compaction and to avoid surface blemishes.

  • Irrigation An irrigation reduced pressure zone (hereinafter referred to as “RPZ”) is required for any irrigation systems and must be installed by the Developer and/or eventual lot owner and tested in accordance with the Minnesota Department of Health Guidelines for Designing Backflow Prevention Assembly Installations (hereinafter referred to as “Guidelines”). The initial test results and certification shall be submitted to the City of Maple Grove Public Works Department. Subsequently, the RPZ must be tested, per the Guidelines, at least annually by a certified tester with the results reported to the City of Maple Grove Building Department and the RPZ must be rebuilt as needed in accordance with the Guidelines. Test/rebuilt reports shall be mailed or faxed to the City of Maple Grove Building Department at (▇▇▇) ▇▇▇-▇▇▇▇. The irrigation system shall be designed and the Plans shall be modified accordingly, prior to the issuance of any permits for the development of the Property, to accommodate a 1-inch water meter and a maximum flow of 50 gallons per minute.

  • Dewatering (a) Where the whole of a site is so affected by surface water following a period of rain that all productive work is suspended by agreement of the Parties, then dewatering shall proceed as above with Employees so engaged being paid at penalty rates as is the case for safety rectification work. This work is typically performed by Employees engaged within CW1, CW2 or CW3 classifications. When other Employees are undertaking productive work in an area or areas not so affected then dewatering will only attract single time rates. (b) Where a part of a site is affected by surface water following a period of rain, thus rendering some areas unsafe for productive work, consistent with the Employer’s obligations under the OH&S Act, appropriate Employees shall assist in the tidying up of their own work site or area if it is so affected. Where required, appropriate Employees will be provided with the appropriate PPE. Such work to be paid at single time rates. Productive work will continue in areas not so affected. (c) To avoid any confusion any ‘dewatering’ time which prevents an Employee from being engaged in their normal productive work is not included in any calculation for the purposes of determining whether an Employee is entitled to go home due to wet weather (refer clauses 32.4 and 32.5)

  • Heating, Ventilation and Air Conditioning Landlord shall furnish to the Premises heating, ventilation and air-conditioning (“HVAC”) in accordance with the Design Standards set forth in Exhibit E during Ordinary Business Hours. Landlord shall have access to all air-cooling, fan, ventilating and machine rooms and electrical closets and all other mechanical installations of Landlord (collectively, “Mechanical Installations”), and Tenant shall not construct partitions or other obstructions which may interfere with Landlord’s access thereto or the moving of Landlord’s equipment to and from the Mechanical Installations. No Tenant Party shall at any time enter the Mechanical Installations or tamper with, adjust, or otherwise affect such Mechanical Installations. Landlord shall not be responsible if the HVAC System fails to provide cooled or heated air, as the case may be, to the Premises in accordance with the Design Standards by reason of (i) any equipment installed by, for or on behalf of Tenant, which has an electrical load in excess of the average electrical load and human occupancy factors for the HVAC System as designed, or (ii) any rearrangement of partitioning or other Alterations made or performed by, for or on behalf of Tenant. Tenant shall install, if missing, blinds or shades on all windows, which blinds and shades shall be subject to Landlord’s approval, and shall keep all of the operable windows in the Premises closed, and lower the blinds when necessary because of the sun’s position, whenever the HVAC System is in operation or as and when required by any Requirement. Tenant shall cooperate with Landlord and shall abide by the rules and regulations which Landlord may reasonably prescribe for the proper functioning and protection of the HVAC System.

  • Heating, Ventilating and Air Conditioning General Office Area: The building shall be equipped with a combination heating, ventilation and air conditioning system. The system shall have ducted supply and return air. The space above the ceiling shall not be used as a supply or return plenum. The systems shall be sized in accordance with the