COMPLETION AND FINAL ACCEPTANCE OF THE WORK Sample Clauses

COMPLETION AND FINAL ACCEPTANCE OF THE WORK. 47.1. Date for Substantial Completion: The Contractor shall substantially complete the Work within the time fixed in Schedule A, or within the time to which such Substantial Completion may be extended. 47.2. Determining the Date of Substantial Completion: The Work will be deemed to be substantially complete when the two conditions set forth below are met.
COMPLETION AND FINAL ACCEPTANCE OF THE WORK. The March 2017 version clarifies Article 14.2.2 concerning the dates to complete punch list work.
COMPLETION AND FINAL ACCEPTANCE OF THE WORK. 14.1 Date for Substantial Completion: The Contractor shall substantially complete the Work for each vessel within the time fixed in Milestone Schedule, or within the time to which such Substantial Completion may be extended (see Book 4, Technical Specifications Section 986 for Substantial Completion and Final Acceptance Criteria). 14.2 Determining the Date of Substantial Completion: The Work for each vessel will be deemed to be substantially complete when the two conditions set forth below have been met.
COMPLETION AND FINAL ACCEPTANCE OF THE WORK. 14.1 The Contractor must complete the work within the time fixed therefor in the Specifications or within the time to which such completion may be extended. 14.2 Final inspection of the work by the Commissioner shall be made within 10 days after receipt of the Contractor's written request therefor. The work will be deemed complete as of the date of such inspection if, upon such inspection, the Director finds that no further work remains to be done. The Commissioner will then issue a certificate of completion and acceptance of the work. However, if such inspection, in the opinion of the Director, reveals items of work still to be performed, the Contractor shall promptly perform them and then request a re-inspection. If, upon any re-inspection, the Director determines that the work is complete; the date of completion shall be deemed to be the actual date of such re-inspection, which shall be made not more than 10 days after the date of the request therefor.

Related to COMPLETION AND FINAL ACCEPTANCE OF THE WORK

  • Acceptance of the Work 19.1 No act of, or failure to act by, the Owner or the OWNER'S REPRESENTATIVE during the course of the Work, nor any extension of time for the completion of the Work, shall be regarded as an acceptance of such Work or any part thereof, or of materials used therein, either wholly or in part. Acceptance shall be evidenced only by the Final Payment by the Owner to Contractor. Before any final certificate shall issue, Contractor shall execute an affidavit on the certificate that it accepts the same in full payment and settlement of all claims on account of Work done and materials furnished under this Contract, and that all claims for materials provided or labor performed have been paid or set aside in full. No waiver of any breach of this Contract by the Owner or anyone acting on Owner's behalf shall be held as a waiver of any other subsequent breach thereof. 19.2 Contractor agrees to guarantee all work under this Contract for a period of one year from the date of Final Payment by the Owner or within such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required under terms of Owner’s conditional acceptance of elements of the Work the Owner deems marginally substandard. If any unsatisfactory condition or damage develops within the time of this guarantee period due to materials or workmanship that are defective, inferior, or not in accordance with the Contract, as reasonably determined by the Owner or the OWNER’S REPRESENTATIVE, then the Contractor shall, when notified by the Owner or OWNER’S REPRESENTATIVE, immediately place such guaranteed Work in a condition satisfactory to the Owner or OWNER’S REPRESENTATIVE. Such guarantee shall be in addition to any implied warranty under law or other manufacturer’s or product supplier’s warranty. The provisions of this Article apply to Work done by Subcontractors as well as to Work done by direct employees of the Contractor, and are in addition to any other remedies or warranties provided by law.

  • FINAL COMPLETION AND FINAL PAYMENT 9.9.1 Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such 9.9.2 Neither the final payment nor the remaining retained percentage shall become due until the Contractor submits to the Architect (1) an affidavit that all payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the State or its property might in any way be responsible, have been paid or otherwise satisfied; (2) consent of surety, if any, to final payment; (3) Other data establishing payment or satisfaction of all such obligations, including, but not limited to, receipts, releases, or other supporting documentation. and (4) final waivers of liens arising out of the Contract, to the extent and in such form as may be designated by the State. If any Subcontractor refuses to furnish a release or waiver required by the State, the Contractor may furnish a bond satisfactory to the State to indemnify him against any such lien. If any such lien remains unsatisfied after all payments are made, the Contractor shall refund to the State all moneys that the latter may be compelled to pay in discharging such lien, including all costs and reasonable attorneys' fees. 9.9.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by the issuance of Change Orders affecting final completion, and the Architect so confirms, the State shall, upon application by the Contractor and certification by the Architect, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Contract Documents, and if bonds have been furnished as required by the Contract Documents, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Architect prior to certification of such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. 9.9.4 The making of final payment shall constitute a waiver of all claims by the State except those arising from: (a) unsettled liens, (b) faulty or defective Work appearing after Substantial Completion, (c) failure of the Work to comply with the requirements of the Contract Documents, or (d) terms of any special warranties required by the Contract Documents. 9.9.5 The acceptance of final payment shall constitute a waiver of all claims by the Contractor except those previously made in writing and identified by the Contractor as unsettled at the time of the final Application for Payment.

  • Final Acceptance All Work has been completed and accepted by the County. The Contractor has provided all required close-out documentation and items as required by the Detailed Scope of Work for the specific Job Order, and these items and have accepted and approved by the County

  • Completion of the Work The Contractor must obtain Material Completion as defined in Section 6.1.2 below prior to any occupancy of the Project.