Conditions of Substantial Completion Sample Clauses

The Conditions of Substantial Completion clause defines the specific requirements that must be met for a construction project or a designated portion of it to be considered substantially complete. This typically includes criteria such as the project being sufficiently finished so that the owner can occupy or use it for its intended purpose, even if minor work or corrections remain. The clause often outlines the process for inspection, documentation, and the formal declaration of substantial completion. Its core practical function is to establish a clear milestone for project delivery, triggering important contractual events like the transfer of responsibility, commencement of warranties, and release of certain payments, thereby reducing ambiguity and potential disputes between parties.
Conditions of Substantial Completion. Substantial Completion is the stage in the progress of the Work (or portion thereof designated and approved by Owner) when the construction is sufficiently complete, in accordance with the Contract Documents, so Owner can fully occupy the Work (or the designated portion thereof) for the use for which it is intended. All Work other than incidental corrective or Punchlist work shall be completed as of Substantial Completion, and Substantial Completion shall not have been achieved if: (a) any systems and parts are not functioning as required by the Contract Documents; (b) utilities are not connected and operating normally; (c) all required occupancy permits have not been issued; or (d) the Work is not accessible by normal vehicular and pedestrian traffic routes.
Conditions of Substantial Completion. Substantial Completion shall have been deemed achieved when each of the following conditions have occurred. (a) the Work is substantially complete and the Project is ready for Operational Readiness Testing; (b) a Certificate of Dynamic Testing Readiness has been executed pursuant to Section 17.3.2; (c) Contractor has delivered and installed all Equipment and Materials required for commencing operations, and all such Equipment and Materials have passed all testing, inspections and safety certifications required under the System Acceptance Plan and the Contract Documents; (d) Contractor has received all applicable Regulatory Approvals which Contractor is obligated under the Contract Documents to obtain for use and operation of the Project; (e) Contractor has successfully completed all of the inspections and tests defined in the System Acceptance Plan, including the System Performance Demonstration Tests, and has demonstrated that the requirements of the Contract Documents for operation of the Project have been met; (f) Owner has received, in acceptable form, all documentation, including as- built information, required to be submitted prior to Substantial Completion in the System Acceptance Plan; (g) Contractor has purchased and delivered to Owner (as directed by Owner), free and clear of Liens, spare parts, spare Equipment and Materials, special tools, materials, expendables and consumables in accordance with the Contract Documents; (h) Contractor has completed all training of personnel in accordance with the Contract Documents; (i) All Defects that materially adversely impact the operation of the Project have been corrected; (j) Contractor has completed preparation of all Punch Lists and has prepared a schedule for the completion of all Punch List items that is acceptable to Owner; (k) Contractor has submitted, in acceptable form, all of the required operations and maintenance plans, procedures, rules, schedules and manuals required by the Contract Documents; (l) Contractor has delivered to Owner copies of Contractor’s final Systems Safety/Security Certification Report and Certificate, as defined by Contractor’s System Safety/Security Certification Management Plan (the format of the System Safety/Security Certification Report and Certificate shall be developed and agreed upon by Owner and Contractor at a reasonable time prior to the expected date of Substantial Completion); and (m) All Liquidated Damages due under the Contract have been paid or otherwise sa...
Conditions of Substantial Completion. Substantial Completion shall have been deemed achieved when each of the following conditions have occurred. (a) Contractor has delivered and installed all Equipment and Materials required for commencing operations, and all such Equipment and Materials have passed all testing, inspections and safety certifications required under the Contract Documents; (b) Contractor has closed out all applicable Regulatory Approvals which Contractor is obligated under the Contract Documents to obtain for use and operation of the Project; (c) Contractor has completed preparation of all Punch Lists and has prepared a schedule for the completion of all Punch List items that is acceptable to Owner.
Conditions of Substantial Completion. Substantial Completion shall have been deemed achieved when each of the following conditions have occurred. (a) the Work is substantially complete, including the close-out of all Regulatory Approvals; (b) Not Used; (c) Not Used; (d) Not Used; (e) Contractor has completed preparation of all Punch Lists and has prepared a schedule for the completion of all Punch List items that is acceptable to Owner; and (f) All Liquidated Damages due under the Contract have been paid or otherwise satisfied.
Conditions of Substantial Completion. Substantial Completion” shall occur when each of the conditions set forth on Exhibit O-5 has been satisfied in accordance with the Specifications.

Related to Conditions of Substantial Completion

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Certificate of Substantial Completion The certificate prepared by the Designer and approved by the Owner to the effect that the Work has reached Substantial Completion.

  • CONDITIONS OF PREMISES A. Within seven (7) days after you move-in, you are required to submit an online Room Condition Update to notify us in writing of any defects or damages in your assigned space (including common area, fixtures, appliances and furniture). Failure to do so will result in the assigned space being considered to be in a clean, safe and good working condition and you will be responsible for defects or damages that may have occurred before you moved in. B. With the exception of the items emailed to you or that you have submitted through the online Room Condition Update, you accept your assigned space, the fixtures, appliances and furniture in their “AS-IS” condition, with any faults. With regard to your assigned space, and the fixtures, appliances and furniture within, we make no express warranties and disclaim any and all implied warranties (other than the warranty of habitability). C. Excluding ordinary wear and tear from normal usage, you will be solely responsible to the Housing Office for damages to your assigned space and the furnishings provided in the assigned space. You are responsible for the cost of all repairs made necessary by you and/or your guest(s) or, as set forth below, any other person in violation of the License. This includes the negligent or careless use of your assigned space or any part of the residence hall, including, without limitation, damage from waste water stoppages caused by foreign or improper objects in lines serving the bathroom used by you, damages to furniture, appliances, doors, windows or screens, damage from windows or doors being left open and repairs or replacements to security devices necessitated by misuse or damage. You may be required to prepay for these repairs, or, if we decide to advance the funds for the repairs, you will be responsible for repaying us within ten (10) days. In addition, you could be charged for damages that may have been caused by other Residents if we cannot determine who did it, and you will be jointly and severally liable for all damages to other shared areas of the assigned space and any furnishings provided in those shared areas. If the party responsible for damages is identified, we may nonetheless determine, in our sole discretion, if you and other potentially responsible parties are allowed to renew for the next year. Your obligations to pay the charges described in this paragraph will continue after the end of this License. D. Furnishings Removal. You assume full responsibility for items furnished by us and agree to return them to us at the end of the License Term in as good condition as when you receive them, reasonable wear and tear excepted. You will be responsible for returning all furniture to its original position prior to vacating your assigned space. You will not remove our furniture, fixtures, and/or furnishings from the assigned space for any purpose.

  • Completion of Repairs Borrower will commence any Repairs as soon as practicable after the date of this Loan Agreement and will diligently proceed with and complete such Repairs on or before the Completion Date. All Repairs and Capital Replacements will be completed in a good and workmanlike manner, with suitable materials, and in accordance with good building practices and all applicable laws, ordinances, rules, regulations, building setback lines and restrictions applicable to the Mortgaged Property. Borrower agrees to cause the replacement of any material or work that is defective, unworkmanlike or that does not comply with the requirements of this Loan Agreement, as determined by Lender.