Continuation of the Work Sample Clauses

The 'Continuation of the Work' clause ensures that work on a project or contract proceeds without interruption, even if disputes or issues arise between the parties. Typically, this clause requires the contractor or service provider to continue performing their obligations while any disagreements are being resolved, such as during negotiations or arbitration. Its core practical function is to prevent project delays and maintain progress, thereby minimizing disruptions and potential losses for all parties involved.
POPULAR SAMPLE Copied 2 times
Continuation of the Work. Unless otherwise agreed in writing, and notwithstanding any other rights or obligations of either of the parties under any Contract Documents or Contracts, the Contractor must carry on with the performance of its contract services and the Work, including all duties and obligations hereunder, during the pendency of any Claim, dispute, and other matter in question or during any alternative dispute resolution proceeding, court proceeding, or other proceeding to resolve any Claim, dispute, and other matter in question, and the Owner will continue to make payments in accordance with the Contract Documents. The Owner, however, is under no obligation to make payments on or against such Claims, disputes, and other matters in question during the time required to resolve such Claims, disputes, and other matters in question.
Continuation of the Work. Unless otherwise agreed in writing, and notwithstanding any other rights or obligations of either of the parties under any Contract Documents or Agreements, the Design-Builder must carry on with the performance of its contract services and the Work, including all duties and obligations hereunder, during the pendency of any claim, dispute, and other matter in question or during any alternative dispute resolution proceeding, court proceeding, or other proceeding to resolve any claim, dispute, and other matter in question, and the Owner will continue to make payments in accordance with the Contract Documents. The Owner, however, is under no obligation to make payments on or against such claims, disputes, and other matters in question during the time required to resolve such claims, disputes, and other matters in question.
Continuation of the Work. Any Work that commences prior to and will extend beyond the expiration date of the current contract period shall, unless terminated by mutual written agreement between the City and the involved Design-Build Firm, continue until completion at the same prices, terms and conditions.
Continuation of the Work. The Contractor shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with the Homeowner.
Continuation of the Work. Unless otherwise agreed in writing, and notwithstanding any other rights or obligations of either of the parties under any Contract Documents or Agreements, the CM/GC must carry on with the performance of its contract services and the Work, including all duties and obligations hereunder, during the pendency of any claim, dispute, and other matter in question or during any alternative dispute resolution proceeding, court proceeding, or other proceeding to resolve any claim, dispute, and other matter in question, and the Owner will continue to make payments in accordance with the Contract Documents. The Owner, however, is under no obligation to make payments on or against such claims, disputes, and other matters in question during the time required to resolve such claims, disputes, and other matters in question.
Continuation of the Work. 32.1 The Contractor shall carry on the Project and adhere to the progress schedule during all disputes or disagreements with the City, subject to the limitations of Article
Continuation of the Work. Unless there is provision that states otherwise in this contract, or there is a written order issued by PEP, the CONTRACTOR shall continue with the services and comply with its obligations pursuant to this contract, notwithstanding the fact that proceeding(s) have been initiated for resolving claims and disputes of a technical or administrative nature, or disputes according to this contract. THIRTY-FIVE TAX CLAUSE. Each of the parties will comply with the pertinent tax obligations, and will pay each and every one of the contributions and other tax charges that they are obligated to pay during the term, execution and fulfillment of this contract and its attachments, pursuant to the federal, state and municipal law of the United Mexican States and the United States of America. The foregoing is without prejudice to the withholdings that PEP is obligated to pay according to the laws in this area.
Continuation of the Work. Pending final resolution of a claim, Contract must proceed diligently with performance of Contractor’s obligations under the Contract.
Continuation of the Work. Subcontractor must diligently continue to prosecute the Work, including all disputed Work, provided that Contractor continues to provide payment for undisputed Work per Article 7, regardless of the existence of a dispute or Claim or the pendency of any dispute resolution procedure or pendency of any civil action.
Continuation of the Work. Unless otherwise agreed in writing, and notwithstanding any other rights or obligations of either of the parties under any Contract Documents or Agreements, the Construction Manager must carry on with the performance of its service and duties hereunder during the pendency of any claim, dispute, and other matter in question or arbitration or other proceeding to resolve any claim, dispute, and other matter in question, and the Owner will continue to make payments in accordance with the Contract Documents. But the Owner is under no obligation to make payments on or against such claims, disputes, and other matters in question during the time required to resolve such claims, disputes, and other matters in question.