Common use of Contractor’s failure to rectify Defects Clause in Contracts

Contractor’s failure to rectify Defects. If the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Engineer. The cost so determined and an amount equal to 20% (twenty percent) of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 50 contracts

Sources: Engineering Procurement and Construction Agreement, Contract Agreement, Construction Contract

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 33 contracts

Sources: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.215.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Authority Engineer. The cost so determined determined, and an amount equal to 20% (twenty percent) of the such cost as Damages Damages, shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 8 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s Contractor‟s cost so as to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Authority‟s Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 6 contracts

Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.215.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Railway Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Engineer. The cost so determined determined, and an amount equal to 20% (twenty percentper cent) of the such cost as Damages Damages, shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 4 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.215.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Railway Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Authority Engineer. The cost so determined determined, and an amount equal to 20% (twenty percent) of the such cost as Damages Damages, shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 3 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement

Contractor’s failure to rectify Defects. If the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Engineer. The cost so determined and an amount equal to 20% (twenty percent) of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 3 contracts

Sources: Construction Contract, Construction Contract, Construction Contract

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.215.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Engineer. The cost so determined determined, and an amount equal to 20% (twenty percentper cent) of the such cost as Damages Damages, shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

Contractor’s failure to rectify Defects. If the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s 's cost to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s 's Engineer. The cost so determined and an amount equal to 20% (twenty percent) of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority Employer shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Project Highway Works conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority Employer and the Contractor, be determined by the AuthorityEmployer’s Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority Employer from the Contractor and may be deducted by the Authority Employer from any monies due to the Contractor.

Appears in 1 contract

Sources: Contract Agreement for Design and Construction

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority Employer shall be entitled to get the same repaired, rectified or remedied at the Contractor’s 's cost so as to make the Project Highway Works conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority Employer and the Contractor, be determined by the Authority’s Employer's Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority Employer from the Contractor and may be deducted by the Authority Employer from any monies due to the Contractor.

Appears in 1 contract

Sources: Epc Agreement

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s Contractor‟s cost so as to make the Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Authority‟s Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 1 contract

Sources: Epc Agreement

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority Authority/GMDA shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Project Highway PROJECT conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority Authority/GMDA and the Contractor, be determined by the Authority’s AUTHORITY’S/GMDAs Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority Authority/GMDA from the Contractor and may be deducted by the Authority Authority/GMDA from any monies due to the Contractor.

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement

Contractor’s failure to rectify Defects. If the Contractor fails to repair or rectify such Defect or deficiency within the period specified spec- ified in Clause 17.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost to make the Project Highway conform to the Specifications Specifica- tions and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Engineer. The cost so determined and an amount equal to 20% (twenty percentper- cent) of the cost as Damages shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 1 contract

Sources: Construction Contract

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.215.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Railway Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Authority Engineer. The cost so determined determined, and an amount equal to 20% (twenty percentper cent) of the such cost as Damages Damages, shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 1 contract

Sources: Epc Agreement

Contractor’s failure to rectify Defects. If In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.215.2, the Authority shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the DFCCIL Project Highway conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority and the Contractor, be determined by the Authority’s Authority Engineer. The cost so determined determined, and an amount equal to 20% (twenty percent) of the such cost as Damages Damages, shall be recoverable by the Authority from the Contractor and may be deducted by the Authority from any monies due to the Contractor.

Appears in 1 contract

Sources: Engineering, Procurement and Construction (Epc) Agreement

Contractor’s failure to rectify Defects. If ‌ In the event that the Contractor fails to repair or rectify such Defect or deficiency within the period specified in Clause 17.2, the Authority Employer shall be entitled to get the same repaired, rectified or remedied at the Contractor’s cost so as to make the Project Highway Works conform to the Specifications and Standards and the provisions of this Agreement. All costs consequent thereon shall, after due consultation with the Authority Employer and the Contractor, be determined by the AuthorityEmployer’s Engineer. The cost so determined and an amount equal to 20% (twenty percent) percent of the cost as Damages shall be recoverable by the Authority Employer from the Contractor and may be deducted by the Authority Employer from any monies due to the Contractor.

Appears in 1 contract

Sources: Demonstration Agreement