Contractor’s Schematic Design Stage Submission. 3.6.1 At the completion of the activities described under Section 3.5 and based on the provisional Schematic Design Documents, the Contractor will submit its Schematic Design Stage Submission. 3.6.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Schematic Design Stage Submission, the Contractor will include in its Schematic Design Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Schematic Design Estimate”). 3.6.2.1 If the Contractor’s Schematic Design Estimate exceeds the Construction Budget or varies from the A/E’s Schematic Design Estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Schematic Design Stage Submission. 3.6.3 If a GMP Amendment has been entered into at the time of the Contractor’s Schematic Design Stage Submission, the Contractor shall include with the Contractor’s Schematic Design Stage Submission a detailed description of any change in the scope of the Work described in the provisional Schematic Design Documents as compared to the scope of the Work described in the GMP Documents and an estimate of the cost and time impact of each change.
Appears in 2 contracts
Sources: Architect/Engineer Agreement, Architect/Engineer Agreement
Contractor’s Schematic Design Stage Submission. 3.6.1 At the completion of the activities described under Section 3.5 and based on the provisional Schematic Design Documents, the Contractor will submit its Schematic Design Stage Submission.
3.6.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Schematic Design Stage Submission, the Contractor will include in its Schematic Design Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Schematic Design Estimate”).
3.6.2.1 If the Contractor’s Schematic Design Estimate exceeds the Construction Budget or varies from the A/E’s Schematic Design EstimateEstimate by more than 5 percent of that estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Schematic Design Stage Submission.
3.6.3 If a GMP Amendment has been entered into at the time of the Contractor’s Schematic Design Stage Submission, the Contractor shall include with the Contractor’s Schematic Design Stage Submission a detailed description of any change in the scope of the Work described in the provisional Schematic Design Documents as compared to the scope of the Work described in the GMP Documents and an estimate of the cost and time impact of each change.
Appears in 1 contract
Sources: Professional Services
Contractor’s Schematic Design Stage Submission. 3.6.1 3.5.1 At the completion of the activities described under Section 3.5 3.4 and based on the provisional Schematic Design Documents, the Contractor will submit its Schematic Design Stage Submission.
3.6.2 3.5.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Schematic Design Stage Submission, the Contractor will include in its Schematic Design Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Schematic Design Estimate”).
3.6.2.1 3.5.2.1 If the Contractor’s Schematic Design Estimate exceeds the Construction Budget or varies from the A/E’s Schematic Design EstimateEstimate by more than 5 percent of that estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Schematic Design Stage Submission.
3.6.3 3.5.3 If a GMP Amendment has been entered into at the time of the Contractor’s Schematic Design Stage Submission, the Contractor shall include with the Contractor’s Schematic Design Stage Submission a detailed description of any change in the scope of the Work described in the provisional Schematic Design Documents as compared to the scope of the Work described in the GMP Documents and an estimate of the cost and time impact of each change.
Appears in 1 contract
Sources: Professional Services