Common use of Contractor’s Submittals Clause in Contracts

Contractor’s Submittals. 3.1.14.1 Prior to submission of any Submittals, the Contractor shall prepare a Submittal schedule, and shall submit the schedule for the Owner’s approval. The Owner’s approval shall not unreasonably be delayed or withheld. The Submittal schedule shall (1) be coordinated with the Contractor’s schedule provided in Section 3.1.12.1, (2) allow the Owner reasonable time to review Submittals, and (3) be periodically updated to reflect the progress of the Work. If the Contractor fails to submit a Submittal schedule, the Contractor shall not be entitled to and waives any increase in Contract Sum or extension of Contract Time based on delay caused by Owner’s review of Submittals.

Appears in 2 contracts

Sources: Engineering, Procurement, and Construction Agreement, Engineering, Procurement, and Construction Agreement