Common use of Correction of Work After Final Payment Clause in Contracts

Correction of Work After Final Payment. Neither the final certificate for payment nor any provision in the Contract Documents shall relieve the Contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom which shall appear within a period of two (2) years from the Date of Completion. The Owner shall give notice of observed defects with reasonable promptness. Such notice shall be in writing to the Engineer and Contractor. All questions arising under this article shall be decided by the Owner or its authorized representative. This warranty shall be in addition to and not in lieu of all other remedies available to the Owner.

Appears in 3 contracts

Sources: Construction Agreement, Construction Agreement, Construction Agreement