Common use of Correction of Work After Substantial Completion Clause in Contracts

Correction of Work After Substantial Completion. In addition to other obligations under this Agreement, if, during the Defect Correction Period, any Work performed by Contractor is found to be Defective, Contractor shall, on a reimbursable basis up to the GMP immediately and on an expedited basis (i) correct such Defective Work, whether by repair, replacement or otherwise, including determining the root cause of the Defective Work and undertaking the necessary work to properly remedy and eliminate such root cause and (ii) repair, clean up and remediate any portions of the Site or the Project damaged or affected by such Defective Work, whether by repair, remediation, replacement or otherwise (the “Corrective Work”). Corrective Work shall include “in and out” corrective work, which includes gaining access for correction, repair or replacement of any Work that has already been installed and requires the removal, disassembly, disconnection, installation, reassembly, reconnection or other physical handling of facilities, equipment, structures or other improvements owned, furnished or installed by Persons or entities other than Contractor. If Owner reasonably believes that any Work is Defective during the Defect Correction Period, Owner shall provide written notice within a reasonable period of time after Owner’s determination to Contractor of such Defect, stating the general nature of such Defect or the issue giving rise to Owner’s belief; provided that, such notice shall not be construed as a condition precedent to Contractor’s obligation to perform Corrective Work. Owner shall provide Contractor with access to the Project sufficient for Contractor to perform its Corrective Work, so long as such activities do not unreasonably interfere with the operation of the Project and subject to any reasonable security or safety requirements of Owner.

Appears in 1 contract

Sources: Turnkey Agreement (Global Clean Energy Holdings, Inc.)

Correction of Work After Substantial Completion. In addition to other obligations under this Agreement, if, during the Defect Correction Period, any Work performed by Contractor is found to be Defective, Contractor shall, on a reimbursable basis up to the GMP immediately and on an expedited basis (i) correct such Defective Work, whether by repair, replacement or otherwise, including determining the root cause of the Defective Work and undertaking the necessary work to properly remedy and eliminate such root cause and (ii) repair, clean up and remediate any portions of the Site or the Project damaged or affected by such Defective Work, whether by repair, remediation, replacement or otherwise (the “Corrective Work”). Corrective Work shall include “in and out” corrective work, which includes gaining access for correction, repair or replacement of any Work that has already been installed and requires the removal, disassembly, disconnection, installation, reassembly, reconnection or other physical handling of facilities, equipment, structures or other improvements owned, furnished or installed by Persons or entities other than Contractor; provided, however, Contractor shall not be liable for any increased costs to access the Defect to perform such Corrective Work to the extent such increased costs are due to Owner’s modification of the Project after Substantial Completion that obstructs Contractor’s access to the Defective Work. If Owner reasonably believes that any Work is Defective during the Defect Correction Period, Owner shall provide written notice within a reasonable period of time after Owner’s determination to Contractor of such Defect, stating the general nature of such Defect or the issue giving rise to Owner’s belief; provided that, such notice shall not be construed as a condition precedent to Contractor’s obligation to perform Corrective Work. Owner shall provide Contractor with access to the Project sufficient for Contractor to perform its Corrective Work, so long as such activities do not unreasonably interfere with the operation of the Project and subject to any reasonable security or safety requirements of Owner.

Appears in 1 contract

Sources: Turnkey Agreement (Global Clean Energy Holdings, Inc.)