Common use of Daily Delay Damages Clause in Contracts

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 14 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date Date, as extended as provided in Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $_______ (“Daily Delay Damages”) for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Daily Delay Damages = Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.Days] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date Date, as extended as provided in Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(111.6(a)(i), Company shall collect and Seller shall pay Daily Delay Damages for each Day following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), ; provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to timely achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 7 contracts

Sources: Energy Storage Power Purchase Agreement, Energy Storage Power Purchase Agreement, Energy Storage Power Purchase Agreement

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 90 Days = Daily Delay Damages.] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 5 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as Date or (if applicable) the expiration of such extended in accordance with Section 13.3 (period that Seller fails to achieve the applicable Guaranteed Project and Reporting Milestone Dates)Milestone; provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), and in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date or (if applicable) the expiration of such extended period that Seller fails to achieve the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 4 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Daily Delay Damages. (1) If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ the Daily Delay Damages for each Day following the tenth ("Daily Delay Damages"10th) following Day after the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] (2) If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the tenth (10th) Day after the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").Section

Appears in 3 contracts

Sources: Energy Storage Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Daily Delay Damages. (1) If a thea Guaranteed Project Milestone (other than Commercial OperationsOperations Date) has not been achieved by the later of the Guaranteed Commercial Operations Date or the expiration of any applicable Guaranteed grace periodGuaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ $ for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Commercial OperationsProject Milestone Date or (if applicable) the expiration of such graceextended period that Seller fails to achieve the Commercial Operations Date, as extended in accordance with Section 13.3 (,applicable Guaranteed Project and Reporting Milestone Dates)Milestone; provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty one hundred eighty (180sixty (60) Days Days. for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] ] (2) If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), and in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date or (if applicable) the expiration of such extended period that Seller fails to achieve the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 1 contract

Sources: Power Purchase Agreement

Daily Delay Damages. (i) If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date Date, as extended as provided in Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ $ (“Daily Delay Damages”) for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Daily Delay Damages = Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] Days] (ii) If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date Date, as extended as provided in Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(111.6(a)(i), Company shall collect and Seller shall pay Daily Delay Damages for each Day following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), ; provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to timely achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").Period”).‌

Appears in 1 contract

Sources: Energy Storage Power Purchase Agreement

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller Subscriber Organization shall pay liquidated damages in the amount of $______ for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller Subscriber Organization shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller Subscriber Organization shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller Subscriber Organization shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 1 contract

Sources: Power Purchase Agreement

Daily Delay Damages. (i) If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date Date, as extended as provided in Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ $ (“Daily Delay Damages”) for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Daily Delay Damages = Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] Days] (ii) If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date Date, as extended as provided in Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(111.6(a)(i), Company shall collect and Seller shall pay Daily Delay Damages for each Day following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 11.4 (Guaranteed Project and Reporting Milestone Dates), ; provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to timely achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 1 contract

Sources: Energy Storage Power Purchase Agreement

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $_______ for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [NoteDRAFTING NOTE: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay DamagesCOMPANY WILL SPECIFY THE DOLLAR AMOUNT OF THE DAILY DELAY DAMAGES.] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 1 contract

Sources: Scheduled and Contingency Capacity Purchase Agreement (Sccpa)

Daily Delay Damages. (1) If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ the Daily Delay Damages for each Day following the tenth ("Daily Delay Damages"10th) following Day after the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] (2) If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the tenth (10th) Day after the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 1 contract

Sources: Energy Storage Purchase Agreement

Daily Delay Damages. If a Guaranteed Project Milestone (other than Commercial Operations) has not been achieved by the applicable Guaranteed Project Milestone Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), Company shall collect and Seller shall pay liquidated damages in the amount of $______ 3,500 for each Day ("Daily Delay Damages") following the applicable Guaranteed Project Milestone Date, as extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates); provided, however, that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for a failure to achieve a Guaranteed Project Milestone by the Guaranteed Project Milestone Date shall not exceed sixty (60) Days for each such missed Guaranteed Project Milestone Date (the "Construction ▇▇▇▇▇ ▇▇ Period"). [Note: Contract Capacity x $50/kW ÷ 180 Days = Daily Delay Damages.] If the Commercial Operations Date has not been achieved by the Guaranteed Commercial Operations Date as extended as provided in Section 13.3 (Guaranteed Project and Reporting Milestone Dates), in addition to any Daily Delay Damages collected pursuant to Section 13.4(a)(1), Company shall collect and Seller shall pay Daily Delay Damages following the Guaranteed Commercial Operations Date, as such date may be extended in accordance with Section 13.3 (Guaranteed Project and Reporting Milestone Dates), provided that the number of Days for which Company shall collect and Seller shall pay Daily Delay Damages for failing to achieve the Guaranteed Commercial Operations Date shall not exceed one hundred eighty (180) Days (the "COD ▇▇▇▇▇ ▇▇ Period").

Appears in 1 contract

Sources: Scheduled and Contingency Capacity Purchase Agreement