Decontamination and Decommissioning Sample Clauses

The Decontamination and Decommissioning clause outlines the responsibilities and procedures for safely cleaning up and dismantling facilities, equipment, or sites that have been exposed to hazardous materials. Typically, this clause specifies which party is responsible for removing contaminants, restoring the site to regulatory standards, and properly disposing of waste materials. For example, it may require the contractor to decontaminate machinery before removal or to ensure that all radioactive or toxic substances are handled according to legal requirements. The core function of this clause is to ensure environmental safety and regulatory compliance while clearly allocating responsibility for the safe closure and cleanup of potentially hazardous operations.
Decontamination and Decommissioning. Upon termination or expiration of the Lease, AMS shall be responsible for the decommissioning and decontamination of the Premises, and all systems and equipment operated thereon by AMS during the term of the Lease. The plans for all such decommissioning and decontamination activities shall be subject to the review and approval of Maxtor. All decommissioning and decontamination shall be conducted in compliance with all Environmental Requirements.
Decontamination and Decommissioning. Except as provided in this Section 7.3, DOE shall remain responsible for all costs associated with the decontamination and decommissioning, as defined in the Act, of AVLIS facilities. If USEC's use or operation of AVLIS facilities increases the costs paid by DOE, exclusive of internal DOE overhead costs and the costs of work performed by DOE employees, for the decontamination and decommissioning of the AVLIS facilities over that which DOE would have incurred in the absence of such use or operation, then USEC shall reimburse DOE for such increased costs incurred.
Decontamination and Decommissioning a. The Department will perform an analysis of impacts and risks of potential disposition modes for the tanks and other facilities of the Center in which the high-level radio- active waste solidified under the project was stored, and facilities, material, and hardware used in connection with the project. The NRC and Depa'rtment project managers will consult on requirements and disposition modes to be analyzed. b. Upon receipt of the Department analysis, the NRC will prescribe decontamination and decommissioning (D&D) require- ments in accordance with the Act. c. The Department will prepare a Project Decommissioning Plan which includes a description of engineering and operating activities to be performed. This plan will be reviewed _ by the NRC and comments provided to the Department. The Department will review and consider the comments provided prior to initiation of D&D operations.
Decontamination and Decommissioning a. The Department will perform an analysis of impacts and risks of potential disposition modes for the tanks and other facilities of the Center in which the high-level radio- active waste solidified under the project was storec, and facilities, material, and hardware used in connection with the project. The NRC and Deoartment project nanagers will consult on requirements and disposition modes to be analyzed. b. Upon receipt of the Department analysis, the NRC will prescribe decontamination and decommissioning (D&D) require- mcnts in accordance with the Act, c. The Department will prepare a Project Decommissioning Plan which includes a description of engineering and operating activities to be performed. This plan will be reviewed by the NRC and comments provided to the Department. The Department will review and consider the comments provided prior to initiation of D&D operations. d. The Department will prepare a Site Status Report. The report will provide: 1) a statement of the D&D requirements prescribed by NRC and an analysis of the extent to which such requirement; have be9n satisfied for those portions of the Center required to be decontaminated and deconmissioned by the Act; and . 2) a description of those portions of the Center in the possession of the Department with particular reference to physical and radiological conditions.
Decontamination and Decommissioning. 1. Disposal of buildings and facilities. The plan should include procedures for disposing of buildings and other facilities. 2. Toxic materials - The procedures for permanently disposing of any toxic or acid forming materials should be provided. 3. Lined pond decommissioning.
Decontamination and Decommissioning. Section 4.7 Permits..................................
Decontamination and Decommissioning. Section 7.4

Related to Decontamination and Decommissioning

  • Decommissioning (a) The Contractor shall submit to the Designated Authority, for its approval, pursuant to sub-paragraph 4.11(d)(v), a Decommissioning Plan for the Development Area and a schedule of provisions for the Decommissioning Costs Reserve. (b) The Decommissioning Plan shall be revised and resubmitted to the Designated Authority for its approval at such times as are reasonable having regard to the likelihood that the Decommissioning Plan (including cost estimates thereunder) may need to be revised. (c) The Contractor shall carry out the Decommissioning Plan substantially in accordance with its terms. (d) Estimates of the monies required for the funding of the Decommissioning Plan shall be charged as Recoverable Costs beginning in the Calendar Year following the Calendar Year in which Commercial Production first occurs. The amount charged in each Calendar Year shall be calculated as follows: (i) The total Decommissioning costs at the expected date of Decommissioning shall first be calculated. (ii) There shall be deducted from such total Decommissioning costs the additions made to the Decommissioning Costs Reserve made, and taken as Recoverable Costs, in all previous Calendar Years together with interest on such Recoverable Costs calculated to the approved date of Decommissioning at the actual or forecast rate of Uplift (whichever is applicable). (iii) The residual Decommissioning costs, resulting from the calculations under sub-paragraph 4.14(d)(i) and (ii), shall then be discounted to the Calendar Year in question at the forecast rate of Uplift for each Calendar Year remaining until the Calendar Year of Decommissioning. (iv) The discounted total of residual Decommissioning costs shall then be divided by the total number of Calendar Years remaining prior to the Calendar Year of Decommissioning itself, including the Calendar Year in question. (v) The resultant amount shall be the addition to the Decommissioning Costs Reserve for the Calendar Year in question. (vi) It is the intention of this provision that the total accumulated provision allowed, including interest calculated to the Calendar Year of Decommissioning at the rate of Uplift, will equal the total Decommissioning costs. (vii) If the amount in sub-paragraph 4.14(d)(v) is a negative amount, then such amount shall be treated as a reduction of Recoverable Costs for the Calendar Year in question.

  • Operating Environment Per specifications given in Ref. [1]

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Remediation If Contractor claims that its products or services satisfy the applicable requirements and standards specified in Section 4.2.1 and it is later determined by HCA that any furnished product or service is not in compliance with such requirements and standards, HCA will promptly inform Contractor in writing of noncompliance. Contractor shall, at no additional cost to HCA, repair or replace the non-compliant products or services within the period specified by HCA. If the repair or replacement is not completed within the specified time, HCA may cancel the Contract, delivery, task order, or work order, or purchase line item without termination liabilities or have any necessary changes made or repairs performed by employees of HCA or by another contractor, and Contractor shall reimburse HCA for any expenses incurred thereby.

  • Periodic Review of Costs of Environmental Compliance In the ordinary course of its business, the Company conducts a periodic review of the effect of Environmental Laws on the business, operations and properties of the Company and its subsidiaries, in the course of which it identifies and evaluates associated costs and liabilities (including, without limitation, any capital or operating expenditures required for clean-up, closure of properties or compliance with Environmental Laws or any permit, license or approval, any related constraints on operating activities and any potential liabilities to third parties). On the basis of such review and the amount of its established reserves, the Company has reasonably concluded that such associated costs and liabilities would not, individually or in the aggregate, result in a Material Adverse Change.