DELAYS IN WORK. If the Contractor is delayed at any time in the progress of the work by any act, authorization, or neglect of the Owner or of the Agency, or by any employee of either, or by any other Contractor employed by the Agency, or by changes ordered in the work, or by bona fide labor disputes, fire, unusual and unforeseeable delays in materials transportation, or by causes beyond the Contractor's control which reasonably justifies the delay, then the time for substantial completion of the work may be extended as determined by the Agency in consultation with the Contractor for such reasonable time as may be necessary to avoid the monetary penalty described in Article X. Such requests or claims for extension shall be submitted in writing to the Agency with a copy to the Contractor prior to the changing the completion date.
Appears in 2 contracts
Sources: Contract to Perform Rehabilitation/Repair Work, Contract to Perform Rehabilitation/Repair Work
DELAYS IN WORK. If the Contractor CONTRACTOR is delayed at any time in the progress of the work by any act, authorization, or neglect of the Owner OWNER or any of the Agency, or by any employee of eitherits employees, or by any other Contractor contractor employed by the AgencyOWNER, or by changes ordered in the work, work or by bona fide labor disputes, fire, unusual and unforeseeable delays in materials transportation, or by causes beyond the ContractorCONTRACTOR's control which that reasonably justifies justify the delay, then the time for substantial completion of the work may be extended as determined by the Agency in consultation with the Contractor OWNER for such reasonable time as may be necessary to avoid the monetary penalty described in Article X. Such requests or claims for extension shall be submitted in writing to the Agency with a copy to the Contractor OWNER prior to the changing the authorized completion date.
Appears in 1 contract