Common use of Dispatch and Scheduling Clause in Contracts

Dispatch and Scheduling. 6.1.1 The SPD shall be required to schedule its power as per the applicable regulations / requirements / guidelines of SERC or any other competent agency (SLDC) and same being recognized by the MSPDCLor any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by MSPDCL from time to time. Any deviation from the Schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the MSPDCL and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of Solar Power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and MSPDCL are the Grid connected entities in respect of the Solar Power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations and its amendments/ clarifications issued by CERC/SERC. DSM charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the clause 9.3 of this PPA.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Dispatch and Scheduling. 6.1.1 The SPD shall be required to schedule its power as per the applicable regulations / requirements / guidelines of SERC CERC / JERC or any other competent agency (SLDC) and same being recognized by the MSPDCLor EDA&N or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by MSPDCL EDA&N from time to time. Any deviation from the Schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the MSPDCL EDA&N and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of Solar Power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and MSPDCL EDA&N are the Grid connected entities in respect of the Solar Power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations and its amendments/ clarifications issued by CERC/SERCregulations. DSM UI charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the clause 9.3 of this PPAconcern JERC regulations.

Appears in 1 contract

Sources: Power Purchase Agreement

Dispatch and Scheduling. 6.1.1 The SPD shall be required to schedule its power as per the applicable regulations / requirements / guidelines of SERC CERC or any other competent agency (RLDC/SLDC) and same being recognized by the MSPDCLor BBMB or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by MSPDCL BBMB from time to time. Any deviation from the Schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the MSPDCL BBMB/SLDC/RLDC and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of Solar Power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and MSPDCL BBMB are the Grid connected entities in respect of the Solar Power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations and its amendments/ clarifications issued by CERC/SERCregulations. DSM charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the clause 9.3 of this PPACERC regulations.

Appears in 1 contract

Sources: Power Purchase Agreement

Dispatch and Scheduling. 6.1.1 The SPD shall be required to schedule its power as per the applicable regulations / requirements / guidelines of SERC or any other competent agency (SLDC) and same being recognized by the MSPDCLor MSPDCL or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by MSPDCL from time to time. Any deviation from the Schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the MSPDCL and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of Solar Power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and MSPDCL are the Grid connected entities in respect of the Solar Power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations and its amendments/ clarifications issued by CERC/SERC. DSM charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the clause 9.3 of this PPA.

Appears in 1 contract

Sources: Power Purchase Agreement

Dispatch and Scheduling. 6.1.1 The SPD shall be required entirely responsible to schedule its power as per the applicable regulations / requirements / guidelines of CERC / SERC /SLDC / RLDC or any other competent agency (SLDC) and same being recognized by the MSPDCLor RLDC/SLDC or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by MSPDCL concerned SLDC/RLDC from time to time. Any deviation from the Schedule schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the MSPDCL Buyer, State Load Dispatch Centres, Regional Power Committees, and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of Solar Power power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and MSPDCL Buyer are the Grid connected entities in respect of the Solar Power contracted under this Agreemententities. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations and its amendments/ clarifications issued by CERC/SERCregulations. DSM charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the clause 9.3 of this PPAconcerned Central/State regulations.

Appears in 1 contract

Sources: Power Purchase Agreement

Dispatch and Scheduling. 6.1.1 The SPD shall be required to schedule its power as per the applicable regulations / requirements / guidelines of SERC or any other competent agency (SLDC) and same being recognized by the MSPDCLor JDA or any other competent authority / agency as per applicable regulation/ law / direction and maintain compliance to the applicable Codes/ Grid Code requirements and directions, if any, as specified by MSPDCL JDA from time to time. Any deviation from the Schedule will attract the provisions of applicable regulation / guidelines / directions and any financial implication on account of this shall be on the account of the SPD. 6.1.2 The SPD shall be responsible for directly coordinating and dealing with the MSPDCL JDA and other authorities in all respects in regard to declaration of availability, scheduling and dispatch of Solar Power and due compliance with deviation and settlement mechanism and the applicable Grid code Regulations, acknowledging that the SPD and MSPDCL JDA are the Grid connected entities in respect of the Solar Power contracted under this Agreement. 6.1.3 The SPD shall be responsible for any deviation from scheduling and for any resultant liabilities on account of charges for deviation as per applicable regulations and its amendments/ clarifications issued by CERC/SERC. DSM charges on this account shall be directly paid by the SPD. 6.1.4 Auxiliary power consumption will be treated as per the clause 9.3 of this PPAPPA regulations.

Appears in 1 contract

Sources: Power Purchase Agreement