DOCUMENTS AT THE SITE. 34.1 The Design-Builder will keep at least 1 copy of the following documents at the Site in good order and available to the Authority: (a) a copy of this Agreement; (b) a copy of all development, building, electrical and plumbing permits and inspection reports; (c) up to date and current Drawings and Specifications, including any shop drawings prepared or obtained in respect of the Work; (d) the Project Management Plan; (e) the Time Schedule; (f) the Quality Management Plan; (g) the Work Plan; and (h) the Health and Safety Plan.
Appears in 1 contract
Sources: Design Build Agreement
DOCUMENTS AT THE SITE. 34.1 32.1 The Design-Builder will keep at least 1 copy of the following documents at the Site in good order and available to the AuthorityOwner:
(a) a copy of this Agreement;
(b) a copy of all development, building, electrical and plumbing permits and inspection reports;
(c) up to date and current all Drawings and Specifications, including any shop drawings prepared or obtained in respect of the Work;
(d) a current and up-to-date set of Record Drawings;
(e) the Project Management Plan;
(ef) the Time Schedule;
(fg) the Quality Management Plan;
(g) the Work Plan; and
(h) the Health and Safety Plan.
Appears in 1 contract
Sources: Design Build Agreement
DOCUMENTS AT THE SITE. 34.1 32.1 The Design-Builder will keep at least 1 copy of the following documents at the Site in good order and available to the Authority:
(a) a copy of this Agreement;
(b) a copy of all development, building, electrical and plumbing permits and inspection reports;
(c) up to date and current all Drawings and Specifications, including any shop drawings prepared or obtained in respect of the Work;
(d) a current and up-to-date set of Record Drawings;
(e) the Project Management Plan;
(ef) the Time Schedule;
(fg) the Quality Management Plan;
(g) the Work Plan; and
(h) the Health and Safety Plan.
Appears in 1 contract
Sources: Design Build Agreement
DOCUMENTS AT THE SITE. 34.1 The Design-Builder will keep at least 1 copy of the following documents at the Site in good order and available to the AuthorityOwner:
(a) a copy of this Agreement;
(b) a copy of all development, building, electrical and plumbing permits and inspection reports;
(c) up to date and current Drawings and Specifications, including any shop drawings prepared or obtained in respect of the Work;
(d) the Project Management Plan;
(e) the Time Schedule;
(f) the Quality Management Plan;
(g) the Work Plan; and
(hg) the Health and Safety Plan.
Appears in 1 contract
Sources: Design Build Agreement
DOCUMENTS AT THE SITE. 34.1 The Design-Builder will keep at least 1 copy of the following documents at the Site in good order and available to the AuthorityOwner:
(a) a copy of this Agreement;
(b) a copy of all development, building, electrical and plumbing permits and inspection reports;
(c) up to date and current all Drawings and Specifications, including any shop drawings prepared or obtained in respect of the Work;
(d) a current and up-to-date set of Record Drawings;
(e) the Project Management Plan;
(ef) the Time Schedule;
(fg) the Quality Management Plan;
(gh) the Work Site Works Plan; and
(hi) the Health and Safety Plan.