During Phase. 2: a) Owner shall have the right to occupy and use the Facility. b) Owner shall provide Contractor with reasonable access to complete all Remaining Work so long as such access does not materially interfere with Owner’s use of the Facility. Such Remaining Work shall be conducted under Owner’s Permit to Work system. c) Owner will transport its personnel to the Facility. d) Owner will perform preventive maintenance on the Facility. e) Contractor shall continue to provide utilities (temporary and permanent) to the Facility as required.
Appears in 2 contracts
Sources: Change Order (Cheniere Energy Inc), Change Order (Corpus Christi Liquefaction, LLC)