Extension of Project Milestone Schedule. (a) Dates in the Project Milestone Schedule [or Works Timetable] may be extended only if any of the following events causes or will cause a material delay in achieving one or more Project Milestones: (i) an Agency Event of Default; (ii) a Force Majeure Event; (iii) a change in the detailed engineering designs and plans reasonably proposed by the Agency as described in Section 5.5.3(a) (Changes after Acceptance); (iv) failure, after due diligence, of the Agency to obtain the Consents from the relevant Local Government Units as described in Schedule 9 (Consents); (v) a delay or failure on the part of the Agency to carry out an obligation under this Agreement, other than an obligation related to payments by the Agency, and which failure or delay directly and proximately prevents the Company from meeting a Project Milestone, unless the delay or failure on the part of the Agency is excused under this Agreement, or is attributable to an action or inaction of the Company, its subcontractors, or agents that is inconsistent with this Agreement; or (vi) in case of discovered articles described in Section 5.10 (Discovered Heritage Resources).
Appears in 2 contracts
Sources: Partnership Agreement, Sample Contract