Extension of time for completion. The Contractor shall be entitled subject to this sub-clause 8.4 [Extension of Time for Completion] to an extension of the Time for Completion if and to the extent that completion for the purposes of sub-clause 10.1 [Taking Over of the Works and Sections] is delayed by any of the following causes (and would not otherwise have been delayed): (a) a Variation (unless an adjustment to the Time for Completion has been agreed under sub-clause 13.3 [Variation Procedure]); (b) a cause of delay giving an entitlement to extension of time under a sub-clause of these Conditions; or (c) any delay, impediment or prevention caused by or attributable to the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site. The Contractor shall not be entitled to an extension of time in the circumstances of (a) to