Common use of EXTENSION OF TIME FOR PERFORMANCE Clause in Contracts

EXTENSION OF TIME FOR PERFORMANCE. 41.1. If performance by the Contractor is delayed for a reason set forth in Article 41.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article and the PPB Rules. 41.2. Any extension of time may be granted only by the ACCO (as set forth below) upon written application by the Contractor.

Appears in 11 contracts

Sources: Supply and Service Agreement, Management and Operation Agreement, Supply and Service Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.146.1. If performance by the Contractor is delayed for a reason set forth in Article 41.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 46 and the PPB Rules. 41.246.2. Any extension of time may be granted only by the ACCO or by the Board for the Extension of Time (hereafter “Board”) (as set forth below) upon written application by the Contractor.

Appears in 10 contracts

Sources: Furnish and Install Agreement, Furnish and Install Agreement, Furnish and Install Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.1. 13.1 If performance by the Contractor is delayed for a reason set forth in Article 41.313.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules. 41.2. 13.2 Any extension of time may be granted only by the ACCO or by the Board for the Extension of Time (hereafter "Board") (as set forth below) upon written application by the Contractor.

Appears in 10 contracts

Sources: Proposal for Bids, Proposal for Bids, Construction Contract

EXTENSION OF TIME FOR PERFORMANCE. 41.113.1. If performance by the Contractor is delayed for a reason set forth in Article 41.313.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules. 41.213.2. Any extension of time may be granted only by the ACCO or by the Board for the Extension of Time (hereafter "Board") (as set forth below) upon written application by the Contractor.

Appears in 9 contracts

Sources: Construction Contract, Construction Contract, Supply and Service Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.146.1. If performance by the Contractor is delayed for a reason set forth in Article 41.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article and the PPB Rules. 41.246.2. Any extension of time may be granted only by the ACCO (as set forth below) upon written application by the Contractor.

Appears in 8 contracts

Sources: Supply and Service Agreement, Furnish and Install Agreement, Furnish and Install Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.1. 13.1 If performance by the Contractor is delayed for a reason set forth in Article 41.313.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 13 and the PPB Rules. 41.2. 13.2 Any extension of time may be granted only by the ACCO or by the Board for the Extension of Time (hereafter “Board”) (as set forth below) upon written application by the Contractor.

Appears in 3 contracts

Sources: Construction Contract, Standard Construction Contract, Proposal for Bids

EXTENSION OF TIME FOR PERFORMANCE. 41.1. If performance by the Contractor is delayed for a reason set forth in Article 41.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article 46 and the PPB Rules. 41.2. Any extension of time may be granted only by the ACCO or by the Board for the Extension of Time (hereafter “Board”) (as set forth below) upon written application by the Contractor.

Appears in 2 contracts

Sources: Supply and Service Agreement, Supply and Service Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.147.1. If performance by the Contractor is delayed for a reason set forth in Article 41.347.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article and the PPB Rules. 41.247.2. Any extension of time may be granted only by the ACCO Commissioner or by the Board for the Extension of Time (hereafter “Board”) (as set forth below) upon written application by the Contractor.

Appears in 2 contracts

Sources: Furnish and Install Agreement, Furnish and Install Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.1. If performance by the Contractor is delayed for a reason set forth in Article 41.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article and the PPB Rules. 41.2. Any extension of time may be granted only by the ACCO (as set forth below) upon written application by the Contractor.

Appears in 1 contract

Sources: Furnish and Install Agreement

EXTENSION OF TIME FOR PERFORMANCE. 41.146.1. If performance by the Contractor is delayed for a reason set forth in Article 41.346.3, the Contractor may be allowed a reasonable extension of time in conformance with this Article and section 4-03(b) of the PPB Rules. 41.2. Any extension of time may be granted only by the ACCO (as set forth below) upon written application by the Contractor.

Appears in 1 contract

Sources: Furnish and Install Agreement