Extra Items. i. Extra items shall be allowed but it should be ensured that at any time it should not exceed the contract limit by 10% also if supplementary agreement has to be executed it shall be done immediately prior to completion of work. ii. The contractor shall before the 15th day of each month, submit in writing to the Executive Engineer a statement of extra items if any that they have executed during the preceding month failing which the contractor shall not be entitled to claim any.