Force Account Change Orders. VPRA may issue a Force Account Change Order if VPRA determines that doing so is beneficial, including if VPRA and Design-Builder are unable to negotiate a price for Extra Work Costs in a Change Order as provided in Section 12.9. VPRA may also issue a Directive Letter with pricing determined on a Force Account basis.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement
Force Account Change Orders. VPRA may issue a Force Account Change Order if VPRA determines that doing so is beneficial, including if VPRA and Design-Builder Contractor are unable to negotiate a price for Extra Work Costs in a Change Order as provided in Section 12.914.9 of these General Terms and Conditions. VPRA may also issue a Directive Letter with pricing determined on a Force Account basis.
Appears in 1 contract
Sources: Construction Manager / General Contractor Agreement