Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required. (b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including: (i) any design, construction and commissioning issues; (ii) the Project Schedules; (iii) any issues arising from reports or documents provided by Project Co or the Consultant; (iv) any quality assurance and safety issues; (v) the Works Reports; (vi) any special matters referred to the Works Committee by Contracting Authority or Project Co; (vii) any community and media relations issues in accordance with Schedule 18 – Communications; (viii) monitoring the Final Commissioning Program; and (ix) any other issues pertaining to the Works. (c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure. (d) The Works Committee shall not have authority to make decisions with respect to or approve: (i) any amendment to or waiver of any provision of this Project Agreement; (ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date; (iii) any Variation; (iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or (v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority NHS, Infrastructure Ontario or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s 's ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority NHS has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment FF&E Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority Authority, MAG or Project Co;
(viiviii) any Proceeding at Risk Matters referred to the Works Committee in accordance with Section 14.6;
(ix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiix) monitoring the Interim Completion Commissioning Program and Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Interim Completion by the applicable Scheduled Phase Interim Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety and security issues, including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunication and Public Engagement Protocol;
(viiiix) any issues related to the Access Management Plan and any issues related to the rules, requirements and restrictions relating to access, rail safety and operations and track protection, all as set out in Schedule 15 – Output Specifications;
(x) monitoring each Interim Commissioning Program and the Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase the applicable requirement(s) for an Interim Completion by the applicable Scheduled Phase Interim Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issueschanges to Service Quality Plans;
(v) the Works Reportsany performance issues;
(vi) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(vii) any interface issues between the Project Co Services, the Hospital FM Services and the Osler Supplied Services;
(viii) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority ▇▇▇▇▇, IO or Project Co;
(viiix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or ▇▇▇▇▇’▇ ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority ▇▇▇▇▇ has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment FF&E Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority the College or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunications Protocol;
(viii) monitoring the Final Commissioning Program; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority the College has a right of consent or in respect of which Contracting Authority the College may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issueschanges to Service Quality Plans;
(v) the Works Reportsany performance issues;
(vi) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(vii) any interface issues between the Project Co Services and the Hospital FM Services;
(viii) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority HHS, IO or Project Co;
(viiix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixx) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or HHS’ ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority HHS has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority the CTC or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority the CTC has a right of consent or in respect of which Contracting Authority the CTC may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Maintenance Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Works Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety and security issues, including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 11.6.
(viii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications and Stakeholder Engagement Obligations;
(viiiix) monitoring the Final Commissioning Programany issues related to Schedule 7 – Mobility Matters; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – 26 - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date Key Works Milestones set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority the City has a right of consent or in respect of which Contracting Authority the City may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority WCH, IO or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Interim Completion by the applicable Scheduled Phase Interim Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority WCH has a right of consent or in respect of which Contracting Authority WCH may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Facilities Management Committee and the FF&E Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority HMQ, MAG or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s Co‟s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority HMQ has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the utilities management subcommittee (the “Utilities Management Subcommittee”) to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issueschanges to Service Quality Plans;
(v) the Works Reportsany changes to Operational Policies, Procedures and Practices;
(vi) any performance issues;
(vii) the development and modification of performance standards for the MCSCS FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the MCSCS Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority IO, MCSCS, ORC or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or MCSCS’ ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateMCSCS Services; or
(viv) any matter with respect to which Contracting Authority IO has a right of consent or in respect of which Contracting Authority IO may exercise have discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term and the TIC Interim Period. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, shall form the utilities management subcommittee (the “Utilities Management Subcommittee”) to receive and review all matters related to the utilities management services and shall form the electronic security system integration subcommittee (the “System Integration Subcommittee”) to receive and review all matters related to Electronic Security System Integration Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term and the TIC Interim Period, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issuesthe recommendations of the System Integration Subcommittee;
(v) the Works Reportsany changes to Operational Policies, Procedures and Practices;
(vi) any performance issues;
(vii) the development and modification of performance standards for the MCSCS FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the MCSCS Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority IO, MCSCS, ORC or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program16 - Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – 24 - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or MCSCS’ ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateMCSCS Services; or
(viv) any matter with respect to which Contracting Authority IO has a right of consent or in respect of which Contracting Authority IO may exercise have discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority SJHC, Infrastructure Ontario or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase Early Occupancy Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Early Occupancy Completion by the applicable Scheduled Phase Early Occupancy Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority SJHC has a right of consent or in respect of which Contracting Authority SJHC may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the utilities management subcommittee (the "Utilities Management Subcommittee") to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issueschanges to Service Quality Plans;
(v) the Works Reportsany performance issues;
(vi) the development and modification of performance standards for the HMQ FM Services, which performance standards shall be based on Good Industry Practice;
(vii) any interface issues between the Project Co Services and the HMQ FM Services;
(viii) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority HMQ, MAG, ORC or Project Co;
(viiix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixx) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s Co‟s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or MAG‟s ability to perform the Scheduled Substantial Completion Date or Final Completion by Courthouse Activities and the Scheduled Final Completion DateHMQ FM Services; or
(viv) any matter with respect to which Contracting Authority HMQ has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment FF&E Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority the College or Project Co;
(vii) any Proceeding At Risk Matter referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority the College has a right of consent or in respect of which Contracting Authority the College may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Bypass Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Bypass Management Committee shall interface with the Equipment Steering Works Committee as and when required.
(b) The Works Bypass Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction joint review of the OM&R Work and commissioning issuesthe Technical Requirements;
(ii) the Project Schedulesany performance issues;
(iii) any issues arising from reports or documents provided by Project Co or the Consultant;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters matter referred to the Works Bypass Management Committee by Contracting Authority the Ministry or Project Co;
(viiiv) any community and media relations issues in accordance with Schedule 18 – Communications12 - Communications Protocol;
(viiiv) monitoring the Final Commissioning Programmatters involving any Railway Company, Railway Agreement, Railway Order, Railway Infrastructure, Utility Company, Utility Agreement or Utility Infrastructure;
(vi) any Integrated Management System issues, including quality assurance, environmental and safety issues;
(vii) any Non-Conformance Reports; and
(ixviii) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Bypass Management Committee shall be final and binding on the Parties. If the Works Bypass Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – 22 - Dispute Resolution Procedure.
(d) The Works Bypass Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion perform the OM&R Work or the performance by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Daterelevant parties of any Governmental Activities; or
(viv) any matter with respect to which Contracting Authority the Ministry has a right of consent or in respect of which Contracting Authority the Ministry may exercise have discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority IO, MCSCS or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority IO has a right of consent or in respect of which Contracting Authority IO may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority HRRH, IO or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority HRRH has a right of consent or in respect of which Contracting Authority HRRH may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority the CTC or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunications Protocol;
(viii) monitoring the Final Commissioning Program; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority the CTC has a right of consent or in respect of which Contracting Authority the CTC may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(viiviii) any Proceeding at Risk Matters referred to the Works Committee in accordance with Section 14.6;
(ix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiix) monitoring the Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services and shall form the electronic security system integration subcommittee (the “System Integration Subcommittee”) to receive and review all matters related to Electronic Security System Integration Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issuesthe recommendations of the System Integration Subcommittee;
(v) the Works Reportsany changes to Service Quality Plans;
(vi) any performance issues;
(vii) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the Hospital FM Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority MHCP, Infrastructure Ontario or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or MHCP’s ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority MHCP has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) the Project Schedulesprovision of the Existing Facilities Services;
(iii) any issues arising from reports or documents provided by joint review of the Project Co or Services and the ConsultantOutput Specifications;
(iv) any quality assurance and safety issuesthe recommendations of the Utilities Management Subcommittee;
(v) the Works Reportsany changes to Service Quality Plans;
(vi) any performance issues;
(vii) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the Hospital FM Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority SJHC, Infrastructure Ontario or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or SJHC’s ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority SJHC has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as cooperative and when required.effective
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Works Schedules;
(iii) any issues arising from reports or documents provided by Project DB Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety and security issues, including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority the City or Project DB Co;
(vii) any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunication and Stakeholder Engagement Obligations;
(viiiix) any issues related to the Construction Access Management Plan and the Traffic and Transit Management Plan and any issues related to the rules, requirements and restrictions relating to access, rail safety and operations and track protection, as set out in Schedule 15 – Output Specifications;
(x) monitoring the Final Testing & Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date Key Work Milestones set out in the Baseline Works ScheduleSchedules, a Scheduled Phase Completion Date, the any Scheduled Substantial Completion Date or the any Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project DB Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, East Substantial Completion by the East Scheduled Substantial Completion Date or East Final Completion by the East Scheduled Final Completion Date;
(v) any change that may materially adversely affect DB Co’s ability to achieve the West Substantial Completion by the West Scheduled Substantial Completion Date or West Final Completion by the West Scheduled Final Completion Date; or
(vvi) any matter with respect to which Contracting Authority the City has a right of consent or in respect of which Contracting Authority the City may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Facilities Management Committee as and when required, and shall form the Equipment Steering Committee to receive and review all matters related to the Equipment.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues, including Project Co M&E Design Issues;
(ii) the identification and resolution of Project SchedulesCo Design Issues and WGH Design Issues pursuant to Section 18.5;
(iii) the Works Schedule;
(iv) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(ivv) any quality assurance and safety issues;
(vvi) the Works Reports;
(vivii) the recommendations of the Equipment Steering Committee;
(viii) the recommendations of the Transition Subcommittee;
(ix) any special matters referred to the Works Committee by Contracting Authority WGH, Infrastructure Ontario or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may may, subject to Section 19, refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any VariationVariation (other than a Variation contemplated by Section 18.5(e) of the Project Agreement);
(iv) any change that may materially adversely affect Project Co’s 's ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority WGH has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority MHCP, Infrastructure Ontario or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority MHCP has a right of consent or in respect of which Contracting Authority MHCP may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) the Project Schedules[Intentionally Deleted];
(iii) any issues arising from reports or documents provided by joint review of the Project Co or Services and the ConsultantOutput Specifications;
(iv) any quality assurance and safety issuesthe recommendations of the Utilities Management Subcommittee;
(v) the Works Reportsany changes to Service Quality Plans;
(vi) any performance issues;
(vii) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the Hospital FM Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority CAMH, Infrastructure Ontario or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or CAMH’s ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority CAMH has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety and security issues, including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunication and Public Engagement Protocol;
(viiiix) any issues related to the Access Management Plan and any issues related to the rules, requirements and restrictions relating to access, rail safety and operations and track protection, all as set out in Schedule 15 – Output Specifications;
(x) monitoring the Interim Commissioning Program and the Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Milestone Payment Completion Date, the Scheduled Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase the requirements for Milestone Payment Completion for the First Milestone Payment by the Scheduled First Milestone Payment Completion Date, Milestone Payment Completion for the Second Milestone Payment by the Scheduled Second Milestone Payment Completion Date, Interim Completion by the applicable Scheduled Phase Interim Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issueschanges to Service Quality Plans;
(v) the Works Reportsany performance issues;
(vi) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(vii) any interface issues between the Project Co Services and the Hospital FM Services;
(viii) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority HRRH, IO or Project Co;
(viiix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixx) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or HRRH’s ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority HRRH has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any Proceeding at Risk Matters referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiiix) monitoring the Phase Commissioning Program and the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority SMH or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunications Protocol;
(viiiix) monitoring each Phase Commissioning Program, the Tower Interim Completion Commissioning Program and the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a any Scheduled Phase Completion Date, the Scheduled Tower Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Tower Interim Completion by the Scheduled Tower Interim Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority SMH has a right of consent or in respect of which Contracting Authority SMH may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority CAMH, Infrastructure Ontario or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning ProgramUtilities/Infrastructure Connections Cash Allowance Items; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority CAMH has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Maintenance Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Scope, both prior to and during the Maintenance Term. The Works Maintenance Committee shall interface with the Equipment Steering Works Committee as and when required.
(b) The Works Maintenance Committee shall be responsible for receiving and reviewing all matters related to the Project Scope (excluding the Design and Construction Works, the Highway Work and the Stage 2 Project Co Delivery Scope), both prior to and during the Maintenance Term, including:
(i) any design, construction joint review of the Maintenance Services and commissioning issuesthe Expanded Output Specifications;
(ii) the Project Schedulesany performance, quality assurance, safety, and security issues, including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight;
(iii) any issues arising from reports special matter referred to the Maintenance Committee by the City or documents provided by Project Co or the Consultant;Co; Amended and Restated Project Agreement Ottawa Light Rail Transit Project REDACTED Execution Version CONFIDENTIAL AND PROPRIETARY Page 58 CAN: 26350049.2 BD-#30398459-v2
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – Communications− Communications and Public Consultation Protocol;
(viiiv) monitoring considering and making recommendations to the Final Commissioning ProgramCity to proceed or not to proceed with a Variation pursuant to Schedule 22 – Variation Procedure to address safety or security issues relating to or arising from the Maintenance Services, including those that may arise from, be identified with, have implications to, or otherwise by having regard to, the Project Scope or the Operations; and
(ixvi) any other issues pertaining to the Project Scope (excluding the Design and Construction Works, the Highway Work and the Stage 2 Project Co Delivery Scope).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Maintenance Committee shall be final and binding on the Parties. If the Works Maintenance Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – − Dispute Resolution Procedure.
(d) The Works Maintenance Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion perform the Maintenance Services or the performance by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Daterelevant parties of any City Activities; or
(viv) any matter with respect to which Contracting Authority the City has a right of consent or in respect of which Contracting Authority the City may exercise have discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(viiviii) any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 14.6;
(ix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiix) monitoring the Phase Commissioning Program, the Tower Interim Completion Commissioning Program and Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Tower Interim Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Tower Interim Completion by the Scheduled Tower Interim Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Bypass Management Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any Integrated Management System issues, including quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority the Ministry or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – Communications12 - Communications Protocol;
(viii) monitoring matters involving any Railway Company, Railway Agreement, Railway Order, Utility Company, Utility Agreement or Utility Infrastructure;
(ix) any environmental matters;
(x) any Non-Conformance Report;
(xi) any issue involving the Final Commissioning ProgramO&M Interim Services; and
(ixxii) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – 22 - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase One Substantial Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a the Phase One Substantial Completion by the applicable Scheduled Phase One Substantial Completion Date, Substantial Completion by the Scheduled Substantial Completion Date, the Phase One Final Completion by the Scheduled Phase One Final Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority the Ministry has a right of consent or in respect of which Contracting Authority the Ministry may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority ▇▇▇▇▇, IO or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiiix) monitoring each Phase Commissioning Program and the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a any Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority ▇▇▇▇▇ has a right of consent or in respect of which Contracting Authority ▇▇▇▇▇ may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) the Project Schedulesprovision of Early Services;
(iii) any issues arising from reports or documents provided by joint review of the Project Co or Services and the ConsultantOutput Specifications;
(iv) any quality assurance and safety issuesthe recommendations of the Utilities Management Subcommittee;
(v) the Works Reportsany changes to Service Quality Plans;
(vi) any performance issues;
(vii) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the Hospital FM Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority NHS, Infrastructure Ontario or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s 's ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or NHS's ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority NHS has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority HMQ or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viii) monitoring the Final Commissioning Program; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion DateMilestone, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority HMQ has a right of consent or in respect of which Contracting Authority HMQ may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Facilities Management Committee and the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority HHS, IO or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications- Communications Protocol;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority HHS has a right of consent or in respect of which Contracting Authority HHS may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority Authority, MCSCS or Project Co;
(viiviii) any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 14.6;
(ix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiix) monitoring each Phase Commissioning Program and the Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a any Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any Proceeding at Risk Matters referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase 1 Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a the requirement(s) for Phase 1 Completion by the applicable Scheduled Phase 1 Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) the Project Schedulesprovision of the Existing Facilities Services;
(iii) any issues arising from reports or documents provided by joint review of the Project Co or Services and the ConsultantOutput Specifications;
(iv) any quality assurance and safety issuesthe recommendations of the Utilities Management Subcommittee;
(v) the Works Reportsany changes to Service Quality Plans;
(vi) any performance issues;
(vii) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(viii) any interface issues between the Project Co Services and the Hospital FM Services;
(ix) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority WCH, IO or Project Co;
(viix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixxi) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or WCH’s ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority WCH has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Facilities Management Committee and the FF&E Steering Committee as and when required...
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority HMQ, MAG or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority HMQ has a right of consent or in respect of which Contracting Authority HMQ may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Facilities Management Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Operational Term. The Works Facilities Management Committee shall interface with the Equipment Steering Works Committee as and when required, and shall form the Utilities Management Subcommittee to receive and review all matters related to the Utilities Management Services.
(b) The Works Facilities Management Committee shall be responsible for receiving and reviewing all matters related to the Project Operations (excluding the Works), both prior to and during the Operational Term, including:
(i) any design, construction and commissioning issuesthe transition from the Existing Facilities to the Facility;
(ii) any joint review of the Project SchedulesCo Services and the Output Specifications;
(iii) any issues arising from reports or documents provided by Project Co or the Consultantrecommendations of the Utilities Management Subcommittee;
(iv) any quality assurance and safety issueschanges to Service Quality Plans;
(v) the Works Reportsany performance issues;
(vi) the development and modification of performance standards for the Hospital FM Services, which performance standards shall be based on the Project Co Proposal Extracts and Good Industry Practice;
(vii) any interface issues between the Project Co Services and the Hospital FM Services;
(viii) any special matters matter referred to the Works Facilities Management Committee by Contracting Authority WGH, Infrastructure Ontario (prior to Final Completion) or Project Co;
(viiix) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications Protocol; and
(ixx) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Facilities Management Committee shall be final and binding on the Parties. If the Works Facilities Management Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – - Dispute Resolution Procedure.
(d) The Works Facilities Management Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s 's ability to achieve a Phase Completion by perform the applicable Scheduled Phase Completion Date, Substantial Completion by Project Co Services or WGH's ability to perform the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion DateHospital Services; or
(viv) any matter with respect to which Contracting Authority WGH has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority HMQ or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – CommunicationsCommunications Protocol;
(viii) monitoring the Final Commissioning Program; and
(ix) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the Scheduled Phase Substantial Completion Date, the Scheduled PGW Substantial Completion Date, the Scheduled Final Completion Date or the Scheduled PGW Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s Co‟s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date;
(v) any change that may materially adversely affect Project Co‟s ability to achieve PGW Substantial Completion by the Scheduled PGW Substantial Completion Date or Final Completion by the Scheduled PGW Final Completion Date; or
(vvi) any matter with respect to which Contracting Authority HMQ has a right of consent or in respect of which Contracting Authority HMQ may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when requiredFacilities Management Committee.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) the recommendations of the Transition Subcommittee;
(vii) any special matters referred to the Works Committee by Contracting Authority IO, MCSCS or Project Co;
(viiviii) any community and media relations issues in accordance with Schedule 18 – Communications16 - Communications Protocol;
(viiiix) review and approval of Development Charges;
(x) monitoring the Final Commissioning Program; and
(ixxi) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d11.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – 24 - Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a the TIC Scheduled Phase Completion Date, the Scheduled Substantial Completion Date, the TIC Scheduled Final Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase TIC Completion by the applicable TIC Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date, TIC Final Completion by the TIC Scheduled Final Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority IO has a right of consent or in respect of which Contracting Authority IO may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Maintenance Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksProject Operations, both prior to and during the Maintenance Period. The Works Maintenance Committee shall interface with the Equipment Steering Works Committee as and when required.
(b) The Works Maintenance Committee shall be responsible for receiving and reviewing all matters related to the WorksSystem Infrastructure, both prior to and during the Maintenance Period, including:
(i) any design, construction joint review of the System Infrastructure and commissioning issuesthe Output Specifications;
(ii) the Project Schedulesany performance issues;
(iii) any issues arising from reports or documents provided by Project Co or the Consultant;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters matter referred to the Works Maintenance Committee by Contracting Authority the City or Project Co;
(viiiv) any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) monitoring the Final Commissioning Program- Communications and Stakeholder Engagement Obligations; and
(ixv) any other issues pertaining to the Project Operations (excluding the Works).
(c) Subject to Section 14.2(d12.2(d), any unanimous decision of the Works Maintenance Committee shall be final and binding on the Parties. If the Works Maintenance Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – 26 - Dispute Resolution Procedure.
(d) The Works Maintenance Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion DateVariation;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion perform the Maintenance and Rehabilitation Services or the performance by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Daterelevant parties of any Governmental Activities; or
(viv) any matter with respect to which Contracting Authority the City has a right of consent or in respect of which Contracting Authority the City may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role.
(a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:including:
(i) any design, construction and commissioning issues;
(ii) the Project Schedules;
(iii) any issues arising from reports or documents provided by Project Co or the ConsultantIndependent Certifier;
(iv) any quality assurance and safety issues;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) any Proceeding at Risk Matters referred to the Works Committee in accordance with Section 14.6;
(viii) any community and media relations issues in accordance with Schedule 18 – Communications;
(viiiix) monitoring the Final Commissioning Program; and
(ixx) any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in the Baseline Works Schedule, a Scheduled Phase Completion Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion by the applicable Scheduled Phase Completion Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the Works. The Works Committee shall interface with the Equipment Steering Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the Works, including:
(i) : any design, construction and commissioning issues;
(ii) ; the Project Schedules;
(iii) ; any issues arising from reports or documents provided by Project Co or the Consultant;
(iv) Independent Certifier; any quality assurance and safety and security issues;
(v) , including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight; the Works Reports;
(vi) ; any special matters referred to the Works Committee by Contracting Authority or Project Co;
(vii) ; any Proceeding At Risk Matters referred to the Works Committee in accordance with Section 14.6; any community and media relations issues in accordance with Schedule 18 – Communications;
(viii) Communication and Public Engagement Protocol; any issues related to the Access Management Plan and any issues related to the rules, requirements and restrictions relating to access, rail safety and operations and track protection, all as set out in Schedule 15 – Output Specifications and Schedule 34 – Rail Corridor Access and Flagging; monitoring the Final Commissioning Program; and
(ix) and any other issues pertaining to the Works.
(c) Subject to Section 14.2(d), any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) : any amendment to or waiver of any provision of this Project Agreement;
(ii) ; any change to a major milestone date set out in the Baseline Works Schedule, a the Kipling Bus Terminal Scheduled Phase Completion Handover Date, the Scheduled Substantial Completion Date or the Scheduled Final Completion Date;
(iii) ; any Variation;
(iv) ; any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion Handover of the [REDACTED] by the applicable [REDACTED], Handover of the Kipling Bus Terminal Essential Components by the Kipling Bus Terminal Scheduled Phase Completion Handover Date, Substantial Completion by the Scheduled Substantial Completion Date or Final Completion by the Scheduled Final Completion Date; or
(v) or any matter with respect to which Contracting Authority has a right of consent or in respect of which Contracting Authority may exercise discretion pursuant to this Project Agreement.
Appears in 1 contract
Sources: Project Agreement
Function and Role. (a) The Works Committee shall assist the Parties by promoting cooperative and effective communication with respect to matters related to the WorksDesign and Construction Works and the Highway Work. The Works Committee shall interface with the Equipment Steering Maintenance Committee as and when required.
(b) The Works Committee shall be responsible for receiving and reviewing all matters related to the WorksDesign and Construction Works and the Highway Work, including:
(i) any design, construction and commissioning issues;
(ii) the Project SchedulesWorks Schedule and the Highway Construction Schedule;
(iii) any issues arising from reports or documents provided by Project Co or the Independent Certifier or the Consultant;
(iv) any quality assurance and safety and security issues, including any design, configuration control, interfacing, training, testing, operational impact and other matters creating or giving rise to a safety or security issue or otherwise requiring attention and oversight;
(v) the Works Reports;
(vi) any special matters referred to the Works Committee by Contracting Authority the City or Project Co;
(vii) any community and media relations issues in accordance with Schedule 18 – Communications− Communications and Public Consultation Protocol;
(viii) monitoring considering and making recommendations to the Final Commissioning ProgramCity to proceed or not to proceed with a Variation pursuant to Schedule 22 – Variation Procedure to address safety or security issues relating to, arising from, or having implications to the planning, implementation or performance of the Project Scope or the Operations, or any part; and
(ix) any other issues or matters pertaining to the Works.Design and Construction Works and the Highway Work. Amended and Restated Project Agreement Ottawa Light Rail Transit Project REDACTED Execution Version CONFIDENTIAL AND PROPRIETARY Page 55 CAN: 26350049.2 BD-#30398459-v2
(c) Subject to Section 14.2(d), 11.2(d) any unanimous decision of the Works Committee shall be final and binding on the Parties. If the Works Committee is unable to reach a unanimous decision, either Party may refer the matter for resolution in accordance with Schedule 27 – − Dispute Resolution Procedure.
(d) The Works Committee shall not have authority to make decisions with respect to or approve:
(i) any amendment to or waiver of any provision of this Project Agreement;
(ii) any change to a major milestone date set out in Scheduled Milestone Acceptance Date, the Baseline Works ScheduleHighway Scheduled Substantial Completion Date, a Highway Scheduled Phase Final Completion Date, the Scheduled Substantial Completion Required Revenue Service Availability Date or the Scheduled Final Completion Date;
(iii) any Variation;
(iv) any change that may materially adversely affect Project Co’s ability to achieve a Phase Completion any Milestone Acceptance by the applicable Scheduled Phase Completion Milestone Acceptance Date, Substantial Completion of the Highway Work by the Highway Scheduled Substantial Completion Date, Highway Final Completion Date by the Highway Scheduled Final Completion Date, the Revenue Service Availability by the Required Revenue Service Availability Date or Final Completion by the Scheduled Final Completion Date; orand
(v) any matter with respect to which Contracting Authority the City has a right of consent or in respect of which Contracting Authority the City may exercise discretion pursuant to this Project Agreement.