Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 105 contracts
Sources: Contract Agreement, Construction Contract, Engineering Procurement and Construction Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 44 contracts
Sources: Engineering, Procurement and Construction Agreement, Draft Contract Agreement, Draft Contract Agreement (Dca)
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 24 contracts
Sources: Engineering Procurement and Construction (Epc) Agreement, Contract Agreement, Contract Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.121.1.
Appears in 18 contracts
Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time anyTime Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.121.1.
Appears in 7 contracts
Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority Employer in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority Employer under this Agreement including the right to termination under Clause 23.1.
Appears in 6 contracts
Sources: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour Endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 3 contracts
Sources: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour endeavor to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 2 contracts
Sources: Epc Agreement, Draft Agreement for RFP for Beautification of Streets
Incomplete Works. 10.5.1 In the event the Contractor fails to complete the Works in accordance with the Project Completion Commissioning Schedule, including any Time Extension granted under this Contract Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Contract Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Contract Agreement to take appropriate action against the Contractor including the right to termination under Clause 23.121.1.
Appears in 2 contracts
Sources: Draft Contract Agreement, Contract Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay shallpay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay fordelay of each day until the Works are completed in accordance with the provisions of this ofthis Agreement. Recovery of Damages under this Clause shall be without prejudice to the tothe rights of the Authority under this Agreement including the right to termination under Clause 23.1.
10.7 MaintenanceManual
Appears in 1 contract
Sources: Construction Contract
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour Endeavour to complete the balance work expeditiously and shall pay Damages to the Authority Authority/GMDA in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority Authority/GMDA under this Agreement including the right to termination under Clause 23.1.
Appears in 1 contract
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority Employer in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority Employer under this Agreement including the right to termination under Clause 23.1.
Appears in 1 contract
Sources: Demonstration Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.. P a g e | 60
Appears in 1 contract
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery Improvement and widening to two lane with paved shoulder of Damages under this Clause shall be without prejudice road from Km 21.100 to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.Km
Appears in 1 contract
Sources: Contract Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with under the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour endeavor to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with under the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with under the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority SPV in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority SPV under this Agreement including the right to termination under Clause 23.121.1.
Appears in 1 contract
Sources: Epc Agreement
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.. Page 63 of 144
Appears in 1 contract
Sources: Construction Contract
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii10.3.(ii) for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 1 contract
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 1 contract
Sources: Construction Contract
Incomplete Works. In the event the Contractor fails to complete the Works in accordance with the Project Completion Schedule, including any Time anyTime Extension granted under this Agreement, the Contractor shall endeavour to complete the balance work expeditiously and shall pay Damages to the Authority in accordance with the provisions of Clause 10.3 (ii) 10.3.2 for delay of each day until the Works are completed in accordance with the provisions of this Agreement. Recovery of Damages under this Clause shall be without prejudice to the rights of the Authority under this Agreement including the right to termination under Clause 23.1.
Appears in 1 contract
Sources: Epc Agreement