Initial Acceptance of Schedules. A. At least ten (10) Days before submission of the first Application for Payment, a conference attended by Design-Build Entity, District’s Representative, and others as appropriate will be held to review for acceptability to District’s Representative the schedules submitted, as required by the Contract Documents. Design-Build Entity shall have an additional ten (10) Days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to Design- Build Entity until acceptable schedules are submitted to District’s Representative. Acceptance of the schedules by District’s Representative will not impose on responsibility for accuracy, for sequencing, scheduling, or progress of the Work, or compliance with the Contract Documents. Acceptance will not interfere with or relieve Design-Build Entity from Design-Build Entity’s full responsibility therefor.