Common use of Initial Acceptance of Schedules Clause in Contracts

Initial Acceptance of Schedules. A. Unless otherwise provided in the Contract Documents, at least ten days before submission of the first Application for Payment a conference attended by Owner’s Representative, CONTRACTOR, ARCHITECT, and others as appropriate will be held to review for acceptability to ARCHITECT as provided below the schedules submitted in accordance with paragraph 2.05.B. CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until acceptable schedules are submitted to the Owner’s Representative and ARCHITECT. 1. The progress schedule will be acceptable to the Owner’s Representative and ARCHITECT if it provides an orderly progression of the Work to completion within any specified Milestones and the Contract Times. Such acceptance will not impose on ARCHITECT responsibility for the progress schedule, for sequencing, scheduling, or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR’s full responsibility therefore. 2. CONTRACTOR’s schedule of Shop Drawing and Sample submittals will be acceptable to the Owner’s Representative and ARCHITECT if it provides a workable arrangement for reviewing and processing the required submittals. 3. CONTRACTOR’s schedule of values will be acceptable to the Owner’s Representative and ARCHITECT as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work.

Appears in 1 contract

Sources: Contract

Initial Acceptance of Schedules. A. Unless otherwise provided in the Contract Documents, at least ten days before submission of the first Application for Payment a conference attended by Owner’s Representative, CONTRACTOR, ARCHITECT, and others as appropriate will be held to review for acceptability to ARCHITECT as provided below the schedules submitted in accordance with paragraph 2.05.B. CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until acceptable schedules are submitted to the Owner’s Representative and ARCHITECT. 1. The progress schedule will be acceptable to the Owner’s Representative and ARCHITECT if it provides an orderly progression of the Work to completion within any specified Milestones Mile- stones and the Contract Times. Such acceptance will not impose on ARCHITECT responsibility for the progress schedule, for sequencing, scheduling, or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR’s full responsibility therefore. 2. CONTRACTOR’s schedule of Shop Drawing and Sample submittals will be acceptable to the Owner’s Representative and ARCHITECT if it provides a workable arrangement for reviewing and processing the required submittals. 3. CONTRACTOR’s schedule of values will be acceptable to the Owner’s Representative and ARCHITECT as to form and substance if it provides a reasonable allocation of the Contract Price to component parts of the Work.

Appears in 1 contract

Sources: Contract