Interim Completion Date Sample Clauses

The Interim Completion Date clause establishes a specific milestone within a project by which certain defined portions of the work must be completed, separate from the final completion date. This clause typically identifies key deliverables or phases that must be finished by the interim date, such as completing structural work before interior finishes begin. Its core practical function is to ensure that critical stages of a project are achieved on schedule, which can help coordinate subsequent activities, manage dependencies, and mitigate delays that could impact the overall project timeline.
Interim Completion Date. Interim Completion Date means the date Completion of the Interim Work is achieved.
Interim Completion Date. The Property Owner projects that in the following years after the execution and adoption of this Agreement, the following percentages of the Undeveloped Lands within the Real Property will be developed: YEAR % COMPLETE 5 10 15 35 20 60 25 85 30 100
Interim Completion Date. If as of the close of business on the ----------------------- applicable Interim Completion Date for a Redwood Unit, Agent shall not have completed ▇▇▇▇▇▇▇ ▇▇▇▇▇ ▇ in respect of such Unit in accordance with the Unit Plans for such Unit, satisfied the conditions set forth in subparagraph (1) of Section 5 hereof and delivered to Owner on Interim Advance Certificate with respect thereto.
Interim Completion Date. The Property Owner projects that during the years after the execution and adoption of this Agreement, the following percentages of the Undeveloped Lands within the Magnolia Property will be developed. 5 25 10 100 The Park/Cemetery Property is substantially completed.

Related to Interim Completion Date

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.