Issuance of Change Orders Sample Clauses

The Issuance of Change Orders clause defines the process by which modifications to the original contract scope, price, or schedule are formally authorized. Typically, this clause outlines the steps required for either party to propose a change, the documentation needed, and the approval process before any work deviating from the original agreement can proceed. By establishing a clear procedure for handling changes, this clause ensures that all adjustments are mutually agreed upon, reducing the risk of disputes and maintaining project control.
Issuance of Change Orders. The Customer may, at any time by a written Change Order, make changes consistent with this Schedule and/or make changes outside the SOW, if mutually agreed by the parties in advance. Such changes may include revisions to Services or Deliverables. All Change Orders shall be subject to requirements and limitations of the applicable law.
Issuance of Change Orders. The CONSORTIUM may, at any time by a written Change Order, make changes within the scope of the Agreement. Such changes may include, without limitation, revisions or additions to Deliverables and Services. All Change Orders shall be subject to requirements and limitations in applicable Federal, State and County law.
Issuance of Change Orders. At any time during the Term, the DIRECTOR may issue a Change Order to increase or decrease the scope of the Work or change plans and specifications, as the DIRECTOR mayfind necessary to accomplish the general purposes of the AGREEMENT. CONTRACTOR shall furnish the services or deliverables set forth in the applicable Change Order in accordance with the requirements of the AGREEMENT plus any special provisions, specifications, or special instructions issued to execute Other Work/Services. The notice of approved changes to the contract will be issued using the form provided in Exhibit D.
Issuance of Change Orders. CalACES CONSORTIUM may, at any time by a written Change Order, make changes within the scope of the Agreement. Such changes may include, without limitation, revisions or additions to QA Deliverables and QA Services. All Change Orders shall be subject to requirements and limitations in applicable Federal, State and County law.
Issuance of Change Orders. The Contracting Officer may, at any time, make changes to this Agreement, including but not limited to changes in: (1) the scope of the Work; (2) the method of performing the Work; and (3) the rate of performance of the Work. Notwithstanding any provision to the contrary, this Agreement cannot be orally modified. All changes shall be made in a writing signed by the Contracting Officer and describing the change ("Change Order").
Issuance of Change Orders. As may be appropriate under the circumstances, a Change Order may be issued directing changes in the Work before an agreement has been reached regarding an equitable adjustment with respect to the change. Notwithstanding any dispute or delay in reaching an agreement regarding an equitable adjustment with respect to a Change, if directed by the Sea Launch Authorized Representative, Astrotech shall immediately proceed to perform the Work in accordance with such written Change Order. Astrotech shall commence the Work contemplated by a Change Order so that all the dates set forth in the Work schedule, as the same may be adjusted, will be met. Failure to commence Work pursuant to a Change Order in a timely fashion shall constitute a default to which the provisions of Article 26, Default shall apply.

Related to Issuance of Change Orders

  • Execution of Change Orders Change Orders shall be signed by the Contractor, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article

  • CHANGE ORDERS AND AMENDMENTS A. Any alterations, additions, or deletions to the terms of this Agreement, which are required by changes in federal or state law or by regulations, are automatically incorporated without written amendment hereto, and shall become effective on the date designated by such law or by regulation. B. To ensure the legal and effective performance of this Agreement, both parties agree that any amendment that affects the performance under this Agreement must be mutually agreed upon and that all such amendments must be in writing. After a period of no less than 30 days subsequent to written notice, unless sooner implementation is required by law, such amendments shall have the effect of qualifying the terms of this Agreement and shall be binding upon the parties as if written herein. C. Customers have the right to issue a change order to any purchase orders issued to the Contractor for the purposes of clarification or inclusion of additional specifications, qualifications, conditions, etc. The change order must be in writing and agreed upon by Contractor and the Customer agency prior to issuance of any Change Order. A copy of the Change Order must be provided by the Contractor to, and acknowledged by, H-GAC.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Notice of Changes If a Party makes a change in its network which it believes will materially affect the interoperability of its network with the other Party, the Party making the change shall provide at least ninety (90) days advance written notice of such change to the other Party.

  • Change Order Process 12.2.1 Contractor shall provide Notice to Owner as soon as practicable, but no later than five (5) Business Days, after the time when Contractor knows of the impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that will impact the Work. Failure to provide such Notice within ten (10) Business Days after the time when Contractor knows of the impact of any Force Majeure Event shall be deemed to be a waiver of the Contractor’s right to receive a Change Order with respect thereto. Such Notice shall, to the extent practicable, specify the estimated impact on the Target Price and/or the Project Schedule, as applicable, the impact upon the various portions of the Work occasioned by reason of such Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, and shall substantiate the foregoing to the satisfaction of Owner. In the event that Contractor does not know or is unable to specify with reasonable certainty the impact upon the Work at the time such Notice is to be delivered, Contractor shall instead provide Owner with a notice of a potential or anticipated impact of any Force Majeure Event, Owner Caused Delay or any other basis for a Change Order that could impact the Work, and shall thereafter provide Owner (and, if requested by Owner, the Independent Engineer) with periodic supplemental Notices during the period that the Force Majeure Event, Owner Caused Delay or any other basis for a Change Order, as applicable, continues, detailing any developments, progress or other relevant information of which Contractor is aware. To the extent Owner (in consultation with the Independent Engineer with respect to a Material Change) agrees with the Contractor’s determination of a Force Majeure Event or Owner Caused Delay or any other basis for a Change Order, as applicable, and the effects thereof, Owner shall notify Contractor of Owner’s acceptance. In the event Owner (in consultation with the Independent Engineer with respect to a Material Change) does not accept the Contractor’s findings, Owner or Contractor shall be permitted to dispute such Change Order in accordance with Article 36, and Contractor shall be paid for any Work performed in respect of such disputed Change Order as provided in Section 12.2.5. 12.2.2 As soon as practicable, and in any event within fifteen (15) Days (or such other period as is mutually agreed by Owner and Contractor) after receipt from Owner of a request for a change or Notice of Owner’s acceptance under Section 12.2.1, Contractor shall submit to Owner a proposal for implementing the change indicating the estimated change to the Target Price and/or the Project Schedule, as applicable. If Owner (having consulted with the Independent Engineer in the case of a Material Change) agrees that the Contractor’s proposal should be implemented, Owner (having consulted with the Independent Engineer in the case of a Material Change) shall issue a Change Order incorporating such proposal. Upon receiving such Change Order, Contractor shall diligently perform the change in accordance with the terms thereof. 12.2.3 Contractor’s proposal required pursuant to Section 12.2.2 shall consist of: (a) a detailed material take-off with supporting calculations in accordance with the pricing structure herein, for pricing the change, (b) revisions, if any, to the Drawings and Specifications, (c) a schedule for the work associated with the proposed change, (d) the effect, if any, to the Target Price and/or the Project Schedule, as applicable, (e) the effect, if any, of the change on the Work, including the Performance Tests and/or Demonstration Tests (or protocol therefor), (f) changes, if any, to any right, liability or obligation of a Party or any other provision hereof and (g) changes, if applicable, to any Applicable Deadline.