Common use of Lane closure Clause in Contracts

Lane closure. The Concessionaire shall not close any lane of the Project Highway for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, and a copy of such permission shall be sent to the Authority. The provisions of Clause 15.7.1 shall not apply to de-commissioning under Clause 15.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-opened for traffic, and in the event of non –payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement.

Appears in 1 contract

Sources: Concession Agreement

Lane closure. The Concessionaire concessionaire shall not close any lane of the Project Highway for the undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three3(three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, necessary and a copy of such permission shall be sent to the Authority. The provisions of Clause 15.7.1 shall not apply to de-commissioning under Clause 15.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (sixs9x) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be been entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-opened for traffic, and in the event of non –non-payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause 15.7.3 shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or and / or Safety Requirementsrequirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5a)0.5% (zero point five per cent) of Performance Security, and (b) 0.1b)0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non-payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –non-payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement.

Appears in 1 contract

Sources: Concession Agreement

Lane closure. The Concessionaire shall (a) A Lane Closure occurs where: (i) the Availability Requirements are not close any lane met; or (ii) a Closing has been arranged on the Contractor’s request in connection with the performance of the Project Highway Work. (b) Notwithstanding (a), no Lane Closure occurs where: (i) the Availability Requirements have not been met owing to a Compensation Event as provided for undertaking maintenance or repair works except with the prior written approval in subsection (e) of the Independent Engineer. Such approval shall be sought by definition thereof and the Concessionaire through a written request Contractor within twice the Correction Deadline period (the second Correction Deadline pursuant to Section 3.5 under (e)) has arranged once again for the Availability Requirements to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, and a copy of such permission shall be sent to the Authoritymet. The provisions of Clause 15.7.1 shall Section 3.5 under (d) apply by analogy; (ii) the situation referred to in Section 2.3 under (a), subsection (i) or (ii), has arisen owing to a Supervening Event that is not apply to de-commissioning a Compensation Event as provided for under Clause 15.6.1 or to closure of any lane for a period not exceeding 2 Section (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cente) of the Performance Security definition thereof; (iii) the Availability Requirements have not been met and the Contractor has applied for every stretch a Closing that meets the requirements of 500 (five hundred) metres or part thereof the procedure referred to in [•] of the Management Specifications, but the road administrator has not approved the request for each day of delay until a Closing. In this case, as soon as the lane road administrator has been refused the Closing request, the Contractor must re-opened apply for traffic, and a Closing to take effect on the next available date for a Closing to be approved by the road administrator. This exception applies as from the date on which the road administrator notifies the Contractor that the Closing has not been approved to the next available date for the Closing to be approved by the road administrator; or (iv) an Availability Requirement has not been met in the event of non –payment of such delinquent amount forthwith first [•] Business Days after the Commencement Date and in any case the Contractor has arranged for this Availability Requirement to be met as yet within 7 twice the Correction Deadline (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire second Correction Deadline pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of Section 3.5 under (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreemente)).

Appears in 1 contract

Sources: DBFM Agreement

Lane closure. 15.7.1 The Concessionaire shall not close any lane of the Project Highway for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, necessary and a copy of such permission shall be sent to the Authority. . 15.7.2 The provisions of Clause 15.7.1 shall not apply to de-commissioning under Clause 15.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. . 15.7.3 Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-re- opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-opened for traffic, and in the event of non –payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause 15.7.3 shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement.

Appears in 1 contract

Sources: Operation and Maintenance Agreement

Lane closure. 15.7.1 The Concessionaire shall not close any lane of the Project Highway Road for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, necessary and a copy of such permission shall be sent to the Authority. . 15.7.2 The provisions of Clause 15.7.1 shall not apply to de-commissioning under Clause 15.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. . 15.7.3 Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-re- opened for traffic, and in the event of non –payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement.Clause

Appears in 1 contract

Sources: Concession Agreement

Lane closure. ‌ 15.7.1. The Concessionaire shall not close any lane of the Project Highway for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, and a copy of such permission shall be sent to the Authority. 15.7.2. The provisions of Clause 15.7.1 shall not apply to de-commissioning under Clause 15.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. 15.7.3. Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-opened for traffic, and in the event of non –payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement.

Appears in 1 contract

Sources: Concession Agreement

Lane closure. 15.7.1 The Concessionaire shall not close any lane of the Project Highway for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, necessary and a copy of such permission shall be sent to the Authority. . 15.7.2 The provisions of Clause 15.7.1 shall not apply to de-commissioning under Clause ▇▇▇▇▇▇ 15.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. . 15.7.3 Upon receiving the permission pursuant to Clause 15.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-opened for traffic, and in the event of non –payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority Damages under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement.Clause

Appears in 1 contract

Sources: Concession Agreement

Lane closure. 14.7.1. The Concessionaire shall not close any lane of the Project Highway for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Contracting Authority, at least 7 (seven) seven)48 days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission offer a response with such modifications as it may deem necessary, necessary and a copy of such permission or rejection shall be sent to the Contracting Authority. 14.7.2. The provisions of Clause 15.7.1 14.7.1 shall not apply to de-commissioning under Clause 15.6.1 14.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. 14.7.3. Upon receiving the permission pursuant to Clause 15.7.114.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-opening such lane, the Concessionaire shall pay Damages to the Contracting Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for every stretch of 500 (five hundred) metres or part thereof for each day of delay until the lane has been re-opened for traffic, and in the event of non –non-payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Contracting Authority, the same shall be recovered by encashment of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed to be in breach of this Agreement and the Authority shall be entitled to recover Damages, to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth Repeated failure to re-open a lane after the period specified in the permission granted pursuant to Clause 15.8.1 may be assessed and specified forthwith by 14.7.1 can under the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt discretion of the O&M Inspection Report or a notice in this behalf from Contracting Authority be grounds for termination which the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Contracting Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account pursue in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreement26.249.

Appears in 1 contract

Sources: Concession Agreement

Lane closure. 17.7.1 The Concessionaire shall not close any lane of the Project Highway for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the AuthorityMPRDC, at least 7 (seven) days before the proposed closure of such lane and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary, necessary and a copy of such permission shall be sent to the Authority. MPRDC. 17.7.2 The provisions of Clause 15.7.1 17.7.1 shall not apply to de-de- commissioning under Clause 15.6.1 17.6.1 or to closure of any lane for a period not exceeding 2 (two) hours in a day at any time of the day and 6 (six) hours in a day at a time specified by the Independent Engineer as off-peak hours when the flow of traffic is comparatively lower. . 17.7.3 Upon receiving the permission pursuant to Clause 15.7.117.7.1, the Concessionaire shall be entitled to close the designated lane for the period specified therein, and in the event of any delay in re-re- opening such lane, the Concessionaire shall pay Damages to the Authority MPRDC calculated at the rate of 0.1% (zero point one per cent) of the Performance Security Average Daily Fee for every stretch of 500 250 (five hundredtwo hundred and fifty) metres metres, or part thereof thereof, for each day of delay until the lane has been re-opened for traffic, and in the event of non –payment of such delinquent amount forthwith and in any case within 7 (seven) days of issue of written notice by Authority, the same . Such damages shall be recovered by encashment MPRDC in accordance with Article 28 of this Agreement. 17.7.4 Notwithstanding anything to the contrary contained in this Agreement, the Annuity of the Performance Security in which case the provisions of Clause 9 hereof shall apply. For the avoidance of doubt, the Damages under this Clause shall not apply to any Capacity Augmentation undertaken by the Concessionaire pursuant to Article 14 hereunder. Damages for breach of O&M obligations In the event that the Concessionaire fails to repair or rectify any defect or deficiency set forth in the Maintenance Requirements within the period specified therein or is in breach of the Maintenance Programme, Maintenance Manual and/or Safety Requirements, it shall be deemed liable to be reduced for any reduction in breach Assured Lane Availability in accordance with Article 28 of this Agreement and any Damages to be paid as specified in the Authority Clause 17.7.3 above shall be entitled in addition to recover Damages, the reduction / adjustment in the Annuity amount to be calculated and paid for each day of delay until the breach is cured, at the higher of (a) 0.5% (zero point five per cent) of Performance Security, and (b) 0.1% (zero point one per cent) of the cost of such repair or rectification as estimated by the Independent Engineer. Recovery of such Damages shall be without prejudice to the rights of the Authority under this Agreement, including the right of Termination thereof, and in the event of non– payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority, the same shall be recovered by encashment of Performance Security in which case the provisions of clause 9 hereof shall apply. The Damages set forth in Clause 15.8.1 may be assessed and specified forthwith by the Independent Engineer; provided that the Authority may, in its discretion, demand a smaller sum as Damages, if in its opinion, the breach has been cured promptly and the Concessionaire is otherwise in compliance with its obligations hereunder. The Concessionaire shall pay such Damages forthwith. Authority’s right to take remedial measures In the event the Concessionaire does not maintain and/or repair the Project Highway or any part thereof in conformity with the Maintenance Requirements, the Maintenance Manual or the Maintenance Programme or Safety Requirements, as the case may be, and fails to commence remedial works within 15 (fifteen) days of receipt of the O&M Inspection Report or a notice in this behalf from the Authority or the Independent Engineer, as the case may be, the Authority shall, without prejudice to its rights under this Agreement including Termination thereof, be entitled to undertake such remedial measures at the risk and cost of the Concessionaire, and to recover its cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum equal to 50% (fifty per cent) of such cost shall be paid by the Concessionaire to the Authority as Damages. For the avoidance of doubt, the right of the Authority under this Clause 15.9.1 shall be without prejudice to its rights and remedies provided under Clause 15.8. In the event of non –payment by Concessionaire of such delinquent amount forthwith and in any case within seven days of issue of written notice by Authority the Authority shall have the right and the Concessionaire hereby expressly grants to the Authority the right to recover the costs and Damages specified in Clause 15.9.1 directly from the Escrow Account, and for that purpose, the Concessionaire hereby agrees to give irrevocable instructions to the Escrow Bank to make payment from the Escrow Account in accordance with the instructions of the Authority under this Clause 15.9.2. Overriding powers of the Authority If in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and, in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may, without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectifying or removing such hardship or danger, as the case may be. In the event that the Concessionaire, upon notice under Clause 15.10.1, fails to rectify or remove any hardship or danger within a reasonable period, the Authority may exercise overriding powers under this Clause 15.10.2 and take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it for rectifying or removing such hardship or danger; provided that the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required hereunder; provided further that any costs and expenses incurred by the Authority in discharge of its obligations hereunder shall be recovered from the Concessionaire in accordance with the provisions of Clause 15.9 along with the Damages specified therein. In the event of a national emergency, civil commotion or any other act specified in Clause 27.3, the Authority may take over the performance of any or all the obligations of the Concessionaire to the extent deemed necessary by it, and exercise such control over the Project Highway or give such directions to the Concessionaire as may be deemed necessary; provided that for the exercise of such overriding powers by the Authority shall be of no greater scope and of no longer duration than is reasonably required in the circumstances which caused the exercise of such overriding powers by the Authority. For the avoidance of doubt, the consequences of such action shall be dealt in accordance with the provisions of Article 27. It is also agreed that the Concessionaire shall comply with such instructions as the Authority may issue in pursuance of the provisions of this Clause 15.10, and shall provide assistance and cooperation to the Authority, on a best effort basis, for performance of its obligations hereunder. Restoration of loss or damage to Project Highway Save and except as otherwise expressly provided in this Agreement, in the event that the Project Highway or any part thereof suffers any loss or damage during the Concession Period from any cause whatsoever, the Concessionaire shall, at its cost and expense, rectify and remedy such loss or damage forthwith so that the Project Highway conforms to the provisions of this Agreementrespective Annuity Payment Period.

Appears in 1 contract

Sources: Concession Agreement