Late Completion. For each day that Substantial Completion is delayed past January 31, 2008, Tenant shall be entitled to a credit as provided below against its Rent otherwise first falling due (exclusive of pre-paid rent) under this Lease during the Initial Term, except to the extent any such delay was caused by a Force Majuere Event. A "Force Majeure Event" means only acts of God, strikes, lockouts, labor troubles, inability to procure materials despite commercially reasonable efforts to do so, discovery of archeologically significant artifacts which halt construction, reasonably unforeseen sub-surface conditions materially delaying project excavation, acts of civil or military authorities, fires, floods and earthquakes. Landlord shall notify Tenant in writing of each delay Landlord contends was caused by a Force Majeure Event within ten (10) business days of its occurrence, describing the impact on the then current construction schedule. More specifically: