Management and Reporting. 43.1 The Parties will perform the activities and responsibilities set out in Schedule 13. 43.2 The CONTRACTOR shall deliver to the AUTHORITY, in the manner and at the times specified in Schedule 13 the reports required by that Schedule. 43.3 The Parties shall ensure that their respective representatives attend the meetings and perform the functions specified in Schedule 13. 43.4 The CONTRACTOR shall notify the AUTHORITY, as soon as reasonably practicable after they come to the CONTRACTOR’s attention, of any events or circumstances that may adversely affect the performance of the Services and the CONTRACTOR’s obligations under this Agreement, in whole or in part, that are reasonably likely to result in any material delay in the provision of the Services, including any relevant: (A) change in the role or status of any Key Personnel; (B) delay or failure of performance under, or termination of, any Subcontract; (C) threat of or planned industrial action, including any strikes or lock-outs; (D) interruption or unavailability of power supplies or telecommunication networks; (E) failure of any system or equipment; or (F) loss or corruption of any Data. 43.5 Where a progress report, or other information pertaining to the progress or performance of either Party of its obligations under this Agreement, is submitted in connection with this Agreement, the submission, receipt and acceptance of such report, or other information, shall not prejudice the rights of either Party under this Agreement.
Appears in 2 contracts
Sources: Contract for Managed Services, Contract for Managed Services
Management and Reporting.
43.1 The Parties will perform the activities and responsibilities set out in Schedule 13.
43.2 The CONTRACTOR shall deliver to the AUTHORITY, in the manner and at the times specified in Schedule 13 the reports required by that Schedule.
43.3 The Parties shall ensure that their respective representatives attend the meetings and perform the functions specified in Schedule 13.
43.4 The CONTRACTOR shall notify the AUTHORITY, as soon as reasonably practicable after they come to the CONTRACTOR’s attention, of any events or circumstances that may adversely affect the performance of the Services and the CONTRACTOR’s obligations under this Agreement, in whole or in part, that are reasonably likely to result in any material delay in the provision of the Services, including any relevant:
(A) change in the role or status of any Key Personnel;
(B) delay or failure of performance under, or termination of, any Subcontract;
(C) threat of or planned industrial action, including any strikes or lock-outs;
(D) interruption or unavailability of power supplies or telecommunication networks;
(E) failure of any system or equipment; or
(F) loss or corruption of any Data.
43.5 Where a progress report, or other information pertaining to the progress or performance of either Party of its obligations under this Agreement, is submitted in connection with this Agreement, the submission, receipt and acceptance of such report, or other information, shall not prejudice the rights of either Party under this Agreement.