METERING AND BILLING. Scheme for metering System will be developed by SPPD with metering at 220 kV side of the 33kV/220kV Solar Park Sub-Station. a) Sale of power from the Solar Park shall be at 220 kV level at 33/220 kV Substation of the solar park. Energy metering system (main, check and standby meter) will be provided at the 220 kV line feeding Solar Power from the Solar Park b) Energy metering System (stand-by meters) will also be provided at the 33/220 kV substation c) Energy Metering System (main, check and standby) shall be provided at 220kV Switch Gear at the Delivery Point d) Meters will be microprocessor based ABT compliant Tri-vector meters meeting CEA requirement. The accuracy class of energy meters will be of 0.2s class. The meter will be capable of metering active & reactive energies both import and export. The meter will indicate maximum demand by integrating the energy for the preset period. The meter will register maximum demand in separate preset periods of the day with provision for recording of tamper/ abnormal events with date and time stampings in its non-volatile memory e) For energy metering, Current transformers will be of 0.2s class and voltage transformers will be of 0.2 class f) The metering and connected equipment shall be provided by SPDs at their cost as per the relevant CERC/AERC regulations g) For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, and the Grid Code, as amended and revised from time to time. The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters installed by them and shall follow relevant metering requirements as intimated by APGCL.
Appears in 3 contracts
Sources: Implementation and Support Agreement, Implementation and Support Agreement, Implementation and Support Agreement