MONITORING OF CONSTRUCTION Sample Clauses
MONITORING OF CONSTRUCTION. 13.1 Monthly progress reports
MONITORING OF CONSTRUCTION.
13.1 Monthly progress reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report on progress of the Construction Works at Project Site and shall promptly give such other relevant information as may be required by the Independent Engineer.
MONITORING OF CONSTRUCTION. 60 ARTICLE 14 CONSTRUCTION COMPLETION CERTIFICATE 61
MONITORING OF CONSTRUCTION. 11.5.1. During construction of the Project, the Concessionaire shall furnish monthly progress reports to the Engineer-in-Charge on the progress of Construction Works, i.e., planned v/s actual progress highlighting the delays along with reasons for delay, EHS standards followed, any shortcomings, near-miss incidence and shall also give such other relevant information as may be required by the Authority. The monthly progress reports shall be submitted no later than 7 (seven) days after the close of each month;
11.5.2. Samples of all products to be used shall be submitted to the Authority. Any damage during construction, to any part of the work, for any reasons, due to rain, storm, or neglect of the Concessionaire, shall be rectified by the Concessionaire, in an approved manner;
11.5.3. During the Construction Period, the Engineer-in-Charge or his/her representative shall inspect the Project at least once in a month and make a report of such inspection the defects or deficiencies, if any, with particular reference to the Scope of Work, the progress of construction, the status of compliance with the Construction Plan and Designs and Drawings. It shall send a report within 7 days of such inspection to the Concessionaire and upon receipt thereof, the Concessionaire shall rectify and remedy the defects and the deficiencies, if any, stated in the Inspection Report. However, such inspections or the submission of Inspection Report by the Engineer-in-Charge shall not relieve or absolve the Concessionaire of its obligations and liabilities, as per the provisions of the Agreement, in any manner whatsoever;
11.5.4. All equipment/machinery/software programs/ applications covered under the Project shall be subjected to inspection / testing by the Engineer-in-Charge or his/her representative on completion & commissioning; and
11.5.5. If the Project In-Charge of the Authority has reasonably determined that the rate of progress of works is such that the Project is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Project-in-Charge in reasonable detail about the steps it proposes to take to expedite the progress and the period within which it shall achieve COD.
MONITORING OF CONSTRUCTION. Monthly progress reports
13.1.1 Until the COD of Phase-II, the Concessionaire shall, within 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority and/or Independent Engineer. In the event that the Concessionaire undertakes the development of any Additional Capacity in accordance with the terms of this Agreement, the provisions of this Article 13 shall apply mutatis mutandis to such capacities.
13.1.2 Notwithstanding anything to the contrary contained in this Agreement, the Authority shall have the right, but not the obligation, to appoint at its cost from time to time and at any time, the additional engineers, including any Government owned entity or Government employee to inspect and monitor the Construction Works.
MONITORING OF CONSTRUCTION. 13.1 Monthly progress reports
13.1.1 Until the COD of Phase I, the Concessionaire shall, within 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority and/or Independent Engineer.
13.1.2 Notwithstanding anything to the contrary contained in this Agreement, the Authority shall have the right, but not the obligation, to appoint at its cost from time to time and at any time, the additional engineers, including any Government owned entity or Government employee to inspect and monitor the Construction Works.
MONITORING OF CONSTRUCTION. 62 13.1 Monthly progress reports 62 13.2 Inspection 62 13.3 Tests 62 13.4 Delays during construction 63 13.5 Suspension of unsafe Construction Works 63 13.6 Video recording 64 ARTICLE 14 65 COMPLETION CERTIFICATE 65 14.1 Tests 65 14.2 Completion Certificate 65 14.3 Provisional Certificate 65 14.4 Completion of Punch List items 66 14.5 Withholding of Provisional Certificate 66 14.6 Rescheduling of Tests 67
MONITORING OF CONSTRUCTION. The Contractor shall measure the success of the OPV Programme against the Contract KPIs. The OPVs shall be constructed in accordance with the Contractor’s internal processes as are in force from time to time. This will include the production by the Contractor of a Requirements and Acceptance Database ("RADb") and a Vessel Acceptance Matrix ("VAM"). The Contractor shall provide copies of the RADb and the VAM to the Authority on the Shared Data Environment. The Authority may attend and witness such events required by the Contractor’s internal process as it wishes such as design reviews, installation inspections, compartment completion inspections, factory inspection, tests of equipment that is acquired by the Contractor for use on the OPV Programme and Engineering Trials. The Authority may also inspect any part of the OPVs as they are constructed and set to work and raise such observations as it may choose. The Contractor shall pay due regard to any such observations made by the Authority. The Contractor shall produce the following categories of documents as part of its internal processes: Test forms; Basin / Harbour Trial Reports; and Sea Trial Reports. Each of these documents may record Defects and other observations for mitigation at a later stage in the OPV Programme including as part of the D3B process. Such documents (once produced) shall be provided to the Authority on the Shared Data Environment for its review and comment, and the Contractor shall pay due regard to any such comments made by the Authority. No later than twelve (12) months prior to Acceptance, the Contractor shall notify the Authority of the actual number of documents that will be produced under Clause 1.159 and the Parties shall then agree in writing which of these shall be signed by the Contractor as a condition to Acceptance. QUALITY ASSURANCE The following DEFSTANs and AQAPs shall apply to this Contract (subject always to Clause 3 (Precedence)) and the Contractor shall procure that such DEFSTANs and AQAPs apply to its sub-contracts to the extent possible: AQAP 2110 (Edition 3 November 2009) NATO Quality Assurance Requirements for Design, Development and Production; DEFSTAN 05-61 Part 1 (Issue 5 August 2010) Quality Assurance Procedural Requirements Part 1 Concessions; AQAP 2105 (Edition 2 November 2009) NATO Requirements for Deliverable Quality Plans; AQAP 2210 (Edition 3 November 2009) NATO Supplementary Software Quality Assurance Requirements to AQAP 2110; DEFSTAN 02-41 (Issue 3 ...
MONITORING OF CONSTRUCTION. 36 ARTICLE 14 TESTS.............................................................................................................. 38
MONITORING OF CONSTRUCTION.
13.1 Monthly progress reports During the Construction Period, the Mine Operator shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Engineer in charge, a monthly report on progress of the Construction Works and installation of Equipment, and shall promptly give such other relevant information as may be required by the Engineer in charge.