Common use of No Time Extension Clause in Contracts

No Time Extension. Except as otherwise provided in Section 6.8.1 with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 14 contracts

Sources: Development Agreement, Development Agreement, Design Build Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 6.7.1 with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 13 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 with regard to New Utilities, no time extension will be allowed on account of: : (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 10 contracts

Sources: Development Agreement, Development Agreement, Design Build Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 3.13.1(a) with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) inaccuracy in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 9 contracts

Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 6.8.1.1 with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) inaccuracy in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 7 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 3.14.1(a) with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) inaccuracy in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 6 contracts

Sources: Development Agreement, Development Agreement, Development Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 6.8.1.1 with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 4 contracts

Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 with regard to New Utilities, no time extension will be allowed on account of: of (a) any delays attributable to any inaccuracy(ies) inaccuracy in the Utility Strip Map; Map or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 4 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 6.5.1.1 with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 3 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

No Time Extension. Except as otherwise provided in Section 6.8.1 6.5.1 with regard to New Utilities, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 3 contracts

Sources: Design Build Contract, Design Build Contract, Design Build Contract

No Time Extension. Except as otherwise provided in Section 6.8.1 with regard to New Utilities, no time extension will be allowed a llowed on account of: : (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.

Appears in 1 contract

Sources: Development Agreement